C ITY OF P LYMOUTH
R ESOLUTION N O. 2018-163
R ESOLUTION A PPROVING A MENDMENT TO THE C ONTRACT FOR THE
Z ACHARY W ATER T OWER P ROJECT (15003)
WHEREAS, the Zachary Water Tower Rehabilitation project is included in the 2018-2022 Capital
Improvement Program; and
WHEREAS, the City has an existing Water Tank Service Contract with KLM Engineering, Inc. for
the Zachary Water Tower; and
WHEREAS, staff believes it to be in the best interest of the City to amend KLM Engineering, Inc.’s
contract to provide additional work that includes interior wet coating removal and replacement
(sweating area), and transducer control box upgrade and modifications and to revise the contract
language related to performance and payment bonds, in addition to reflecting the variable rate payback
plan which the City Council approved per Resolution 2017-392.
NOW, THEREFORE BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH,
MINNESOTA, that the amendment to the contract dated December 12, 2017 with KLM Engineering, Inc.
is approved to include the additional work for interior wet coating removal and replacement (sweating
areas), and transducer control box upgrade and modifications for an additional cost of $13,960.00 and
revise the contract language related to payment (variable payment plan), and performance and
payment bonds, and that the Mayor and City Manager are authorized and directed to execute the first
amendment to the contract.
APPROVED by the City Council on this 24th day of April, 2018.