Loading...
HomeMy WebLinkAboutCity Council Resolution 2018-163 C ITY OF P LYMOUTH R ESOLUTION N O. 2018-163 R ESOLUTION A PPROVING A MENDMENT TO THE C ONTRACT FOR THE Z ACHARY W ATER T OWER P ROJECT (15003) WHEREAS, the Zachary Water Tower Rehabilitation project is included in the 2018-2022 Capital Improvement Program; and WHEREAS, the City has an existing Water Tank Service Contract with KLM Engineering, Inc. for the Zachary Water Tower; and WHEREAS, staff believes it to be in the best interest of the City to amend KLM Engineering, Inc.’s contract to provide additional work that includes interior wet coating removal and replacement (sweating area), and transducer control box upgrade and modifications and to revise the contract language related to performance and payment bonds, in addition to reflecting the variable rate payback plan which the City Council approved per Resolution 2017-392. NOW, THEREFORE BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH, MINNESOTA, that the amendment to the contract dated December 12, 2017 with KLM Engineering, Inc. is approved to include the additional work for interior wet coating removal and replacement (sweating areas), and transducer control box upgrade and modifications for an additional cost of $13,960.00 and revise the contract language related to payment (variable payment plan), and performance and payment bonds, and that the Mayor and City Manager are authorized and directed to execute the first amendment to the contract. APPROVED by the City Council on this 24th day of April, 2018.