HomeMy WebLinkAboutCity Council Resolution 2018-073
C ITY OF P LYMOUTH
R ESOLUTION N O. 2018-073
R ESOLUTION A PPROVING R EQUEST FOR P AYMENT N O. 4 AND F INAL
2018 M ILL & O VERLAY U TILITY M AINTENANCE – S TORM & S ANITARY S EWER P ROJECT
(189004.001)
WHEREAS, the City of Plymouth as the owner and Klein Underground, LLC as the
contractor, have entered into an agreement for the 2018 Mill & Overlay Utility Maintenance –
Storm & Sanitary Sewer Project, said agreement was approved by the City Council on April 25,
2017; and
WHEREAS, the Engineer has certified his acceptance of the work and his approval of the
final request for payment.
NOW, THEREFORE BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PLYMOUTH, MINNESOTA:
1. That the original contract amount was $566,291.00 and that the value of the work
to date is $549,206.80 and is approved. The final contract amount is $17,084.20,
or 3%, below the original contract amount.
2. That the work performed by the contractor for the 2018 Mill & Overlay Utility
Maintenance – Storm & Sanitary Sewer Project and certified to the Council by the
engineer as acceptable, being the same, is released from the contract except as to
the conditions of the performance bond, any and all legal rights of the owner,
required guarantees and correction of faulty work after final payment.
3. Request for Payment No. 4 and Final in the amount of $36,431.09 to Klein
Underground, LLC for the 2018 Mill & Overlay Utility Maintenance – Storm &
Sanitary Sewer Project is approved and the Administrative Services Director is
authorized and directed to pay the same forthwith.
4. Funding for this project will be from Street Reconstruction Fund in the amount of
$370,354.59 and from the Sewer Fund in the amount of $206,312.55.
APPROVED by the City Council on this 27th day of February, 2018.