HomeMy WebLinkAboutCity Council Resolution 2010-147CITY OF PLYMOUTH
RESOLUTION No. 2010-147
A RESOLUTION APPROVING PAYMENT NO. 9 AND FINAL
WELL NO. 16 PUMPING FACILITY
CITY PROJECT NO. 7114
WHEREAS, the City of Plymouth as owner and Fendler Patterson Constuction,
Inc. as contractor, have entered into an agreement for the Well No. 16 Pumping Facility,
City Project No. 7114, said agreement was approved by the City Council on January 27,
2009; and
WHEREAS, the Engineer has certified his acceptance of the work and his approval
of the final request for payment.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY
COUNCIL OF THE CITY OF PLYMOUTH, MINNESOTA
1. That the original contract amount was $536,578.36, the revised contract amount was
$570,659.36 and the value of work to date is $568,904.86 and is herewith approved.
2. That the work performed by the contractor for the Well No. 16 Pumping Facility and
certified to the Council by the engineer as acceptable, being the same, is hereby
released from the contract except as to the conditions of the performance bond, any
and all legal rights of the owner, required guarantees and correction of faulty work
after final payment.
3. Request for Payment No. 9 and Final in the amount of $28,445.24 to Fendler Patterson
Constriction, Inc. for the Well No. 16 Pumping Facility is hereby approved and the
City's Administrative Services Director is hereby authorized and directed to pay the
same forthwith. Funding for the total project cost will be from the Utility Trunk Fund.
APPROVED THIS 8TH DAY OF JUNE, 2010.