HomeMy WebLinkAboutCity Council Resolution 1998-531CITY OF PLYMOUTH
RESOLUTION NO. 98-531
REQUEST FOR PAYMENT NO. 5 AND FINAL
WESTBRANCH 3" ADDITION - PHASE II
UTILITY AND STREET IMPROVEMENTS
CITY PROJECT NO. 4015
WHEREAS, the City of Plymouth as owner and Kober Excavating, Inc. as contractor,
have entered into an agreement for Westbranch 3'a Addition - Phase II, Utility and Street
Improvements, City Project No. 4015, said agreement being dated August, 1996; and
WHEREAS, the Engineer has certified his acceptance of the work and his approval of the
final request for payment.
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF
THE CITY OF PLYMOUTH, MINNESOTA:
1. That the original contract amount was $277,545.74. One change order
was approved in the amount of $10,352.50 and the value of the work to
date is $276,478.65 and is herewith approved. This project underran the
revised contract amount by $11,419.59 or 4.0%.
2. That the work performed by the contractor for Westbranch -1 Addition -
Phase II, Utility and Street Improvements and certified to the Council by
the engineer as acceptable, being the same, is hereby released from the
contract except as to the conditions of the performance bond, any and all
legal rights of the owner, required guarantees and correction of faulty work
after final payment.
3. Request for Payment No. 5 and Final in the amount of $43,898.73 to
Kober Excavating, Inc. for Westbranch 3'd Addition - Phase II, Utility and
Street Improvements is hereby approved and the City Finance Director is
hereby authorized and directed to pay the same forthwith.
Adopted by the City Council on September 2, 1998.
C \Document, and Settuig, e,uigei Local Settuigs TempCCR 1998-5315896- CCR 1998-531 doe