HomeMy WebLinkAboutCity Council Resolution 2001-315CITY OF PLYMOUTH
RESOLUTION NO. 2001-315
APPROVING CHANGE ORDER NO. 4
LIFT STATION NO. 2 RENOVATION
CITY PROJECT NO. 8030
WHEREAS, Change Order No. 4 has been prepared providing extra compensation to the contractor for
the following:
I . Additional bituminous removal on East Medicine Lake Blvd.
2. Additional concrete curb and gutter.
3. Additional bituminous sawing.
4. Additional 16 -inch megalugs on forcemain to avoid existing utilities.
5. Install two additional precast manholes due to changes in the sanitary sewer alignment.
6. Additional select granular borrow material due to poor subgrade soils.
7. Additional geotextile fabric due to poor subgrade soils.
8. Additional aggregate and bituminous base material.
9. An additional section of storm sewer pipe had to be salvaged and replaced.
AND WHEREAS, Change Order No. 4 for Lift Station No. 2 Renovation, City Project No. 8030, is
recommended for approval;
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PLYMOUTH, MINNESOTA: That Change Order No. 4 to Rice Lake Contracting Inc. for Lift Station
No. 2 Renovation, City Project No. 8030, by adding $41,259.00 is approved:
Original Contract Amount
PREVIOUS CHANGE ORDERS - Add
THIS CHANGE ORDER NO. 4 - Add
REVISED CONTRACT AMOUNT
Adopted by the City Council on July 24, 2001
$1,164,400.00
$ 180,574.00
$ 41,259.00
$1,386,233.00
('_ 35 ('CR ?00131?.doc