HomeMy WebLinkAboutCity Council Resolution 2002-440CITY OF PLYMOUTH
RESOLUTION NO. 2002-440
APPROVING CHANGE ORDER NO. 2
PLYMOUTH BLVD. MEDIAN IMPROVEMENTS
CITY PROJECT #2003
WHEREAS, Change Order No. 2 has been prepared for Soil excavation of medians 4 &
5; and
WHEREAS, Soil excavation exceeded the original Engineers estimate; and
WHEREAS, Change Order No. 2 for Plymouth Blvd. Median Improvements, City
Project No. 2003, is recommended for approval,
NOW, THEREFORE, BE IT RESOLVED BY THE PLYMOUTH CITY COUNCIL that
Change Order No. 2 to Frattalone Excavating & Grading, Inc. for Plymouth Blvd.
Median Improvements, City Project 42003, by adding $13,400 is approved:
Original Contract Amount
$195,362.50
Previous Change Orders
Subtract
20,208.00
Change Order 42
Add
13,400.00
Revised Contract Amount
$188,554.50
Adopted by the City Council on September 24, 2002.