HomeMy WebLinkAboutCity Council Resolution 2002-190CITY OF PLYMOUTH RESOLUTION NO. 2002-190 REDUCING REQUIRED FINANCIAL GUARANTEE HARVEST HILLS (2001023) WHEREAS, in accordance with the development contract dated September 10, 2001 and revised on March 28, 2002, Town and Country Homes, developer of Harvest Hills (2001023), has agreed to install certain improvements for said development; and WHEREAS, the required financial guarantee in the Development Contract (42001023) has been amended as noted below; and WHEREAS, the developer has completed a portion of the street, utility and site grading as noted below; and WHEREAS, the developer has requested a reduction of the required financial guarantee to reflect the completed work; NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH, MINNESOTA; that the financial guarantee requirements are reduced as follows: C Documents and Settnig,unfiee,eLocal Settmg, TempVC(R 2002-19053-1- CCR 2002-190 doe ORIGINAL CURRENT NEW ITEM AMOUNT AMOUNT AMOUNT Street Constriction $ 376,676 $ 263,673 $ 263,673 Schmidt Lake Road Street Constriction 195,886 48,972 48,972 Sanitary Sewer 179,572 89,786 89,786 Watermain 114,780 57,390 57,390 Watermain - Schmidt Lake Road 36,470 9,118 -0- Watermain - Holly Lane 59,809 59,809 59,809 Storm Sewer 283,505 141,752 141,752 Boulevard and Drainage Swale Sod 9,400 9,400 9,400 Rain Garden 5,000 5,000 5,000 N[ -]RP Pond Constriction 73,770 73,770 73,770 Street Signs (2 x 200) 400 400 400 Concrete Sidewalk 35,249 35,249 35,249 Park and Trail Improvements 22,069 22,069 22,069 Site Grading and Drainage Improvements 287,969 71,992 71,992 Setting Iron Monuments 8,000 8,000 8,000 Design, Administration, Inspection, As-Builts 202,627 107,566 106,471 TOTAL $ 1,891,182 $ 1,003,946 $ 993,733 C Documents and Settnig,unfiee,eLocal Settmg, TempVC(R 2002-19053-1- CCR 2002-190 doe Resolution No. 2002-190 Page 2 That the required financial guarantee for the above items be reduced as detailed above from $1,505,919 ($1,003,946 x 150%) to $1,490,600 ($993,733 x 150%) to reflect the completed work. Subdivision Bond No. 929219099 may be reduced accordingly. FURTHER BE IT RESOLVED that the financial guarantee requirements for the following items per Section 8.1 of the approved Development Contract remain as follows: ITEM Maintenance of Erosion and Sediment Control Plan, Street Sweeping, and Storm Sewer Cleaning (see Grading Permit for Financial Guarantee Requirements) Cash: Financial Guarantee: ORIGINAL NEW AMOUNT AMOUNT $ -0- $_0_ $ -0- $ -0- $_0_ FURTI­IER -0- FURTHER BE IT RESOLVED that the Schmidt Lake Road watermain constriction is accepted for continuous maintenance as of April 23, 2002 subject to the two-year guarantee by the Developer per Maintenance Bond No. 54-12332 issued by United Fire and Casualty Company. Adopted by the City Council on April 23, 2002. C Documents and Settnig,unfiee,eLocal Settmg, TempVC(R 2002-19053-1- CCR 2002-190 doe