WHEREAS, Change Order No. 3 has been prepared for the retaining wall modifications
of medians four and five and additional electrical work and photo cell installation; and
WHEREAS, retaining wall installation and electrical work exceeded the original
Engineer's design; and
WHEREAS, Change Order No. 3 for Plymouth Boulevard median improvements, City
Project No. 2003, is recommended for approval;
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF
THE CITY OF PLYMOUTH, MINNESOTA, that Change Order No. 3 to Frattalone
Excavating & Grading, Inc. for Plymouth Boulevard median improvements, City Project
No. 2003, by adding $8,640 is approved:
Original Contract Amount
$195,362.50
Previous Change Orders Subtract
$ 20,208.00
Change Order No. 2 Add
$ 13,400.00
Change Order No. 3 Add
$ 8,640.00
Revised Contract Amount
$197,194.50
Adopted by the City Council on November 10, 2003.