Loading...
HomeMy WebLinkAboutCity Council Resolution 2003-322CITY OF PLYMOUTH RESOLUTION NO. 2003 - 322 APPROVING CHANGE ORDER NO. 1 PEONY LANE/TROY LANE BITUMINOUS PAVING CITY PROJECT NO. 1029 WHEREAS, Change Order No. 1 has been prepared providing for the following: The addition of a new 30 -inch culvert under Peony Lane, south of Elm Creek; change in the grade of asphalt used for the project from PG 58-34 to 58-28; repair of bituminous pavement areas damaged as a result of the winter suspension of the project; and the placement of topsoil as part of the final restoration. WHEREAS, Change Order No. 1 for Peony Lane/Troy Lane Bituminous Paving project, City Project No. 1029, is recommended for approval; NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH, MINNESOTA: That Change Order No. 1 for Peony Lane/Troy Lane Bituminous Paving project, City Project No. 1029, by deducting $4,093.57 is approved: Original Contract Amount $332,322.05 Previous Change Orders $0.00 THIS CHANGE ORDER NO. 1 - $4,093.57 Deduct REVISED CONTRACT AMOUNT $328,228.48 Adopted by the City Council on July 22, 2003. C:ADoc=cnts and Settingsubaird\Local Settings\Temp\CCR 2003-322_53040ACCR 2003-322.doc