HomeMy WebLinkAboutCity Council Resolution 2015-103CITY OF PLYMOUTH
RESOLUTION No. 2015-103
RESOLUTION APPROVING CHANGE ORDER AND FINAL PAYMENT FOR THE
PLYMOUTH ICE CENTER DRYLAND TRAINING FACILITY PROJECT (40021)
WHEREAS, On June 10, 2014, the City Council authorized the construction of a 7,500 square foot
training facility addition onto the Plymouth Ice Center; and
WHEREAS, RJM Construction Company (RJM) was hired as the construction manager for the dry
land training facility; and
WHEREAS, the project consisted of one bid category for the precast structural concrete and
22 quote categories; and
WHEREAS, the architect and construction manager and City staff have reviewed and
accepted all work on this project and are recommending approval of all change orders and final
payments.
Bid Category
Award
Change Orders
Final Payment
Hanson Structural Precast, Inc.
1 $244,696.00
1 (-) 295.00
$244,401.00
Quote Category
Award
Change Orders
Final Payment
Midwest Specialty
$1,862.00
(-)1,862.00
$0
Kellington Const.
$10,310.00
(-)$2,486.71
$7,823.29
Donald Frantz Concrete
$99,950.00
$0
$99,950.00
Central MN Fabricating
$63,800.00
$3,457.05
$67,257.05
Everest Steel, Inc.
$16,900.00
$1,600.00
$18,500.00
Kellington Const.
$28,450.00
(-)$2,383.03
$26,066.97
Top -All Roofing
$57,650.00
$6,280.00
$63,930.00
Glewwe Doors
$14,249.00
(-)$2,393.41
$11,855.59
Empirehouse Inc.
$21,125.00
$3,400.00
$24,525.00
Stern Drywall, Inc.
$59,815.00
$3,734.00
$63,549.00
Kirk Acoustics, Inc.
$3,270.00
$2,900.00
$6,170.00
Mars Carpet Sales
$2,415.00
$0
$2,415.00
Shield Fire Protection
$17,970.00
$935.00
$18,905.00
Horwitz/NSI
$37,400.00
(-)$2,880.00
$34,520.00
Allan Mechanical
$48,320.00
(-)$9,300.00
$39,020.00
Mayer Electric
$79,321.00
$2,731.50
$82,052.50
Veit
$65,900.00
$0
$65,900.00
Atlas Foundations
$89,100.00
$28,386.80
$117,486.80
Veit
$42,950.00
$4,170.00
$47,120.00
Northwest Asphalt
$26,998.00
$345.00
$27,342.00
Stapf Concrete
$14,564.00
$1,066.00
$15,630.00
NOW, THEREFORE BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH,
MINNESOTA, that all change orders and final payments are hereby approved.
FURTHERMORE, BE IT RESOLVED that the overall project cost is $1,329,761 and will be financed
utilizing an internal loan from the Capital Improvement Fund, lease revenue and contributions from the
Wayzata Youth Hockey Association.
APPROVED by the City Council on this 14th day of April, 2015.