HomeMy WebLinkAboutCity Council Resolution 2012-148CITY OF PLYMOUTH
RESOLUTION No. 2012-148
A RESOLUTION RECEIVING PRELIMINARY ENGINEERING REPORT, ORDERING
PREPARATION OF PLANS AND SPECIFICATIONS, AND CALLING FOR A PUBLIC HEARING
FOR THE PLYMOUTH BLVD MILL AND OVERLAY PROJECT
CITY PROJECT NO. 12006
WHEREAS, pursuant to a resolution of the City Council adopted May 8, 2012, a report
has been prepared with reference to the improvement of the area including Plymouth Blvd, from
State Highway 55 to Rockford Road. The project also includes concrete sidewalk replacement on
34t1' Avenue, from Plymouth Blvd to Fernbrook Lane and on Trenton and Nathan Lane, north of
Bass Lake Road, concrete replacement at the Plymouth Creek Center and concrete sidewalk
installation from the east property line of 15725 37th Avenue to approximately 175 feet south of
15800 37th Avenue; and
WHEREAS, the proposed improvement includes the resurfacing of streets by mill and
overlay, replacement of concrete curb and gutter and sidewalk and all necessary appurtenances;
and
WHEREAS, said report is being received by the Council on May 8, 2012; and
WHEREAS, the report provides information regarding whether the proposed project is
necessary, cost effective, and feasible.
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF
THE CITY OF PLYMOUTH, MINNESOTA:
1. The Council will consider the improvement of such streets in accordance with
the report and the assessment of abutting and adjacent property within the
designated Plymouth Blvd Mill and Overlay Project, City Project No. 12006
for all or a portion of the cost of the improvement pursuant to Minnesota
Statutes 429.011 to 429.111 (Laws 1953, Chapter 398, as amended) at an
estimated total cost of the improvement of $732,139.60.
2. A public hearing shall be held on such proposed improvement on the 26th day
of June, 2012 in the Council Chambers of the Plymouth City Center at 3400
Plymouth Boulevard at 7:00 p.m., and the Clerk shall give mailed and
published notice of such hearing and improvements as required by law.
3. The Plymouth Engineering Department is designated as engineer for the
improvement. They shall prepare plans and specifications for the making of
such improvement.
Approved this 8th day of May, 2012.