HomeMy WebLinkAboutCity Council Resolution 2012-037CITY OF PLYMOUTH
RESOLUTION No. 2012-037
A RESOLUTION TO APPROVE A SITE PLAN AMENDMENT FOR
ST. JUDE MEDICAL TO CONSTRUCT A 275,000 -SQUARE FOOT BUILDING ADDITION,
PARKING EXPANSION AND RELATED SITE IMPROVEMENTS LOCATED AT
5050 NATHAN LANE (2011081)
WHEREAS, St. Jude Medical has requested approval of a site plan amendment to
constrict a 275,000 -square foot building addition, parking expansion and related site
improvements for property legally described as:
Lot 1, Block 1, and Outlot A, Northwestern Bell Plymouth Office I" Addition, according
to the recorded plat thereof, Hennepin County, Minnesota.
WHEREAS, the Planning Commission has reviewed said request at a duly called public
meeting and recommends approval.
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF
THE CITY OF PLYMOUTH, MINNESOTA, that it should and hereby does approve the request
by St. Jude Medical, for a site plan amendment to allow a 275,000 -square foot building addition,
parking expansion and related site improvements, subject to the following conditions:
1. A site plan amendment is approved for to allow a 275,000 -square foot building addition,
parking expansion and related site improvements, in accordance with the plans received by
the city on December 13, 2011 and revised plans received on January 3, 2012, and January
12, 2012, except as may be amended by this resolution.
2. A separate building permit is required prior to commencement of the project.
3. Prior to issuance of a building permit, the applicant shall fulfill the requirements, submit
the required information, and revise the plans as indicated below, consistent with the
applicable city code, zoning ordinance, and engineering guidelines:
a. Complete a site improvement performance agreement and submit a financial guarantee
pursuant to section 21045.10 of the zoning ordinance.
b. Update the tree inventory inconsistency between the site demolition plan series and the
tree inventory/tree removals plan (sheet 222.1).
c. Submit a sound source control plan that shows how the site will comply with the city's
noise ordinance.
d. Add a "one-way" sign at the entrance to the loading area and "do not enter" signage at
the south, exit -only access.
Resolution 2012-037
File No. 2011081
Page 2
e. Easements:
1. Submit drainage and utility easements over the existing ponds, wetlands and
drainage area along the service road.
2. Modify the existing 20 -foot sewer and drainage easement, recorded as document
no. 4132015, to center the easement on the existing 24 -inch reinforced concrete
pipe (RCP) storm sewer.
f. Agreements:
1. Revise the current maintenance agreement for the two existing water quality
ponds, recorded as document number 6361600 and the existing 12 -inch storm
water pipe under the building. The revised maintenance agreement shall reflect
the new 24 -inch storm sewer pipe, the three underground storm water treatment
facilities. The revised maintenance agreement shall also reflect maintenance of
the storm sewer system during high water time periods.
2. Submit an encroachment agreement for concrete pavement and retaining walls
that are located within existing easements.
g. Applicable Permits:
1. Shingle Creek Watershed Management Organization.
2. NPDES.
3. MPCA — Sanitary Sewer Extension
4. MDH — Water Main Extension
5. Minnesota Department of Transportation
h. Grading and Drainage Plan:
1. Submit plans at 22 -inch by 34 -inch for record plans.
2. Update plans to show the delineated wetland boundary.
3. Show normal water levels (NWL) and high water levels (HWL) for existing
wetlands.
4. Show a concrete pedestrian ramp at trail connection with the west parking lot.
i. Utility Plan:
1. Identify stricture dimensions and casting numbers for each stricture shown on a
storm sewer stricture schedule.
2. All storm sewer shall be inspected by the Plymouth Engineering Division. Call
763-509-5500 to schedule inspections. Provide a video inspection report for all
new storm sewer lines, underground treatment devices, and the existing 24 -inch
storm sewer pipe.
3. Insulate between new water main and storm sewer pipe where clearance is less
than three feet.
4. Keep drain tile out of existing easements.
5. Show trail to be replaced where connecting to the existing sanitary sewer.
6. Restore the Nathan Lane street surface within 48 hours of making the sanitary
sewer crossing.
7. Maintain existing sanitary sewer flow when sewer connection is made.
8. Use current city standard details, dated 3-11, on details ST -5, ST -6 and ST -9.
Resolution 2012-037
File No. 2011081
Page 3
9. A pressure test and bacteriological test is required for the new water main before
placing it into service.
10. Eliminate short-circuiting of drainage through underground storm water system
A.
j. Water Resources Plan:
1. Submit calculations that demonstrate an 85 -percent reduction in total suspended
solids (TSS) for new impervious areas. A 60 -percent reduction in total
phosphorus (TP) loading for new impervious areas is also required.
2. Demonstrate that post -development rates of runoff are less than pre -development
rates for the 10 -year and 100 -year frequency rainfall events.
3. Demonstrate that volume reduction requirements are satisfied for the 2 -year
rainfall event.
k. Fire Protection Plan:
1. Relocate the two hydrants to approved locations. Locate the west hydrant to an
approved location that is not in a parking space location or a fire lane sign will be
required at the current identified location.
2. The fire apparatus turning radius proofs shall indicate that the apparatus do not
come in contact with any objects, extend into parking spaces or extend over curbs.
3. Fire lane sign locations will be identified by the fire inspector on submitted plans
and in the field.
4. Prior to the issuance of any interior build -out permits, St. Jude Medical shall supply the
city with the maximum number of employees that they would have in the building at one
time. The employee total shall include the employees in the entire building plus any new
employees expected to use the new space under the interior build -out permit.
5. Prior to final inspection approval of the building addition completion, the applicant shall
constrict a traffic signal and any related improvements at the intersection of Schmidt Lake
Road and Nathan Lane.
6. Silt fence shall be installed prior to any constriction on the site.
7. All rooftop equipment shall be screened or painted to match the building.
8. Standard Conditions:
a. The applicant shall remove any diseased or hazardous trees.
b. New signage shall receive sign permits when required and shall comply with the section
21155 of the zoning ordinance.
c. Any subsequent phases or expansions are subject to required reviews and approvals per
ordinance provisions.
d. The site plan shall expire one year after the date of approval, unless the applicant has
substantially started constriction of the project, or unless the applicant has received prior
approval from the city to extend the expiration date for up to one additional year, as
regulated under section 21045.09 of the zoning ordinance.
Resolution 2012-037
File No. 2011081
Page 4
APPROVED THIS 24TH DAY OF JANUARY, 2012.
STATE OF MINNESOTA)
COUNTY OF UENNEPIN) SS
The undersigned, being the duly qualified and appointed City Clerk of the City of Plymouth,
Minnesota, certifies that I compared the foregoing resolution adopted at a meeting of the
Plymouth City Council on January 24, 2012, with the original thereof on file in my office, and
the same is a correct transcription thereof.
WITNESS my hand officially as such City Clerk and the Corporate seal of the City this
day of
City Clerk