HomeMy WebLinkAboutCity Council Resolution 1997-370CITY OF PLYMOUTH
RESOLUTION No. 97.370
APPROMNG CHANGE ORDER NO.2
1995 TRAIL EM PROVEMENTS
CITY PROJECT NO. 417
WHEREAS, Change Order No. 2 has been prepared providing for the following:
The addition of quantities for storm sewer, painting bituminous curb, landscaping
materials, increase in unit price for sodding and seeding. granular and common
borrow; and
WHEREAS, Change Order No. 2 for 1995 Trail Improvemerts, City Project No. 417, is
recommended for approval;
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PLYMOUTH, MINNESOTA: 7Ut Change Order No. 2 to Driveway Design
for the 1995 Trail Improvements, City Project No. 417, by adding $2,656.46 is approved:
Original Contract Amount
Previous Change Order - Add
THIS CHANGE ORDER NO.2 - Add
REVISED CONTRACT AMOUNT
Adopted by the City Council on June 18. 1996.
$332,421.85
37.172.50
2,656.46
$372,250.81