HomeMy WebLinkAboutCity Council Resolution 1993-803CITY OF PLYMOUTH
RESOLUTION 93 -803
REQUEST FOR PAYMENT NO. 1 AND FINAL
1993 SEAL COAT PROGRAM
WHEREAS, the City of Plymouth as owner and Allied Blacktop Company as
contractor, have entered into an agreement for 1993 Seal Coat Program, said agreement
being dated August 3, 1993; and
WHEREAS; the City Engineer has certified acceptance of the work and approval of the
final request for payment.
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF
THE CITY OF PLYMOUTH, MINNESOTA:
I. That the original contract amount was $182,644.80. One change order in the
amount of $7,323.75 was approved and the value of the work to date is
$189,968.55 and is herewith approved.
2. That the work performed by the Contractor for 1993 Seal Coat Program and
certified to the Council by the City engineer as acceptable, being the same, is
hereby released from the contract except as to the conditions of the performance
bond, any and all legal rights of the owner, required guarantees and correction of
faulty work after final payment.
3. Request for Payment No. 1 and Final in the amount of $189,968.55 to Allied
Blacktop Company for 1993 Seal Coat Program is hereby approved and the City
Finance Director is hereby authorized and directed to pay the same forthwith.
Adopted by the City Council on December 20, 1993.