RESOLUTION NO. 93-59
REDUCING DEVELOPMENT BOND
BASS CREEK BUSINESS PARK ADDITION (89061)
WHEREAS, in accordance with the development contract revised and dated June 12, 1990,
Opus Corporation and Schneider (USA), Inc., developer of Bass Creek Business Park
Addition (89061) has agreed to install certain improvements for said development; and
WHEREAS, the developer has completed a portion of the street, utility and site grading
as noted below; and
WHEREAS, the developer has requested a reduction of the development bond to reflect the
completed work;
NOW, THEREF7RE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH that
the bonding requirements are reduced as follows:
Street Construction
Right Turn Lane County Road 10
Sanitary Sewer
Watermain
Storm Sewer
Compensatory Wetland
Water Quality Ponds
Street Signs (2 x 150)
Sidewalks
Site Grading & Drainage Improvements
Design, Administration,
Inspection, As-Builts
ORIGINAL TOTAL
TOTAL PROJ. NO. 008
$1,720,437
_46 33.324 33.360
$ 336 $311,024 $311,360
* Includes final wear course on Nathan Lane from County road 10 to 860 feet north of
County Road 10 at an estimated cost of $10,000.
** The trails not within street right-of-way are private in accordance with Item No.
14, Resolution No. 89-701.
QR_T.NAL
AMOUNT
City Proj.
No. 008
211bllcl
Private
Original
Total
$647,520 *
$ -n-
$ -0-
$ -0-
10,000
-0-
-0-
101,722
-0-
-0-
-0-
195,088
-0-
-0-
-0-
396,281
-0-
-0-
-0-
-0-
-0-
60,700
60,700
322,281
-0-
-0-
-0-
-0-
300
-0-
300
47,545 **
-0-
-0-
-0-
-0-
-0-
217,000
217,000
$1,720,437
_46 33.324 33.360
$ 336 $311,024 $311,360
* Includes final wear course on Nathan Lane from County road 10 to 860 feet north of
County Road 10 at an estimated cost of $10,000.
** The trails not within street right-of-way are private in accordance with Item No.
14, Resolution No. 89-701.
BASS CREEK BUSINESS PARK ADDITION
Resolution No. 93- S9
Page Two
ITEM
ORIGINAL
AMOUNT
City Proj.
Original
No. 008
Public
Private
Tot it
Street Construction
$647,520 *
$ -0-
$ -0-
Right Turn Lane County
Road 10 10,000
-0-
-0-
Sanitary Sewer
101,722
-0-
-0-
-0-
Watermain
195,088
-0-
-0-
-0-
Storm Sewer
396,281
-0-
-0-
-0-
Compensatory Wetland
-0-
-0-
-0-
-0-
Water Quality Ponds
322,281
-0-
-0-
-0-
Street Signs (2 x 150)
-O-
-0-
-0-
-0-
Sidewalks
47,545 **
-O-
-0-
-0-
Site Grading & Drainage
Improvements -0-
-0-
-0-
-0-
Design, Administration,
Inspection, As-Builts
-0-
_0_
-0-
ORIGINAL TOTAL
$ -0-
$ -0-
$ -0-
TOTAL PROJ. NO. 008
$1,720,437
* Includes final wear course on Nathan Lane from County road 10 to 860 feet north of
County Road 10 at an estimated cost of $10,000.
** The trails not within street right-of-way are private in accordance with Item No.
14, Resolution No. 89-701.
That the letter of credit required for the above items (excluding Project No. 008)
hereby reduced as detailed above from $243,376 to $0 (zero).
FURTHER BE IT RESOLVED that the bonding requirements for the following items per
Section 8.1 of the approved development contract be reduced as follows:
ITEM ORIGINAL AMOUNT NEW AMOUNT
Maintenance of Erosion and
Sediment Control Plan,
Street Sweeping and Storm
Sewer Cleaning Cash: $ 11000 $ 1,000
Letter of Credit: $ 72,200 $ 5,000
FURTHER BE IT RESOLVED that the required financial guarantees for the above items
remain at $1,000 cash with the required Letter of Credit No. 73818 being reduced from
$60,000 to $5,000).
Adopted by the City Council on January 25, 1993.