HomeMy WebLinkAboutCity Council Resolution 2004-098CITY OF PLYMOUTH
RESOLUTION NO. 2004-098
REQUEST FOR PAYMENT NO. 3 AND FINAL
2003 STREET MILL AND OVERLAY IMPROVEMENTS
CITY PROJECT NO. 2028
WHEREAS, the City of Plymouth as owner and Midwest Asphalt Corporation, as
contractor, have entered into an agreement for the 2003 Street Mill and Overlay
Improvements Project, City Project No. 2028, said agreement being dated June 6, 2003;
and
WHEREAS, the Engineer has certified acceptance of the work and recommends approval
of the final request for payment;
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF
THE CITY OF PLYMOUTH, MINNESOTA:
1. That the original contract amount was $309,143.10. The value of the
work to date is $298,054.95 and is herewith approved. This project is
$11,088.15 or 3.6% less than the original contract amount.
2. That the work performed by the contractor for the 2003 Street Mill and
Overlay Improvements Project and certified to the Council by the engineer
as acceptable, being the same, is hereby released from the contract except
as to the conditions of the performance bond, any and all legal rights of
the owner, required guarantees and correction of faulty work after final
payment.
3. Request for Payment No. 3 and Final in the amount of $22,360.36 to
Midwest Asphalt Corporation for the 2003 Street Mill and Overlay
Improvements Project is hereby approved and the City Finance Director is
hereby authorized and directed to pay the same forthwith.
4. The fiinding for this project is from the Infrastructure Replacement Fund
(407).