HomeMy WebLinkAboutCity Council Resolution 2004-017CITY OF PLYMOUTH
RESOLUTION NO. 2004-017
ACCEPTING UTILITIES FOR CONTINUAL MAINTENANCE
CASCADES (2002058)
WHEREAS, in accordance with the development contract dated November 6, 2002, Lundgren Bros.
Constriction, Inc., developer of Cascades (2002058), has agreed to install certain improvements for said
development; and
WHEREAS, the developer has completed a portion of the street, utility and site grading as noted below; and
WHEREAS, the developer has requested a reduction of the required financial guarantee to reflect the
completed work;
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PLYMOUTH, MINNESOTA; that the financial guarantee requirements remain as follows:
ITEM
Street Constriction
Sanitary Sewer
Watermain
Storm Sewer
Boulevard and Drainage Swale Sod
Rain Garden Constriction
N [_]RP Pond Constriction
Street Signs (5 x 200)
Park and Trail Improvements
Site Grading and Drainage Improvements
Setting Iron Monuments
Design, Administration, Inspection, As-Builts
TOTAL
ORIGINAL CURRENT NEW
AMOUNT AMOUNT AMOUNT
$ 172,429
$ 146,565
$ 34,486
100,741
20,148
-0-
132,335
26,467
-0-
119,068
23,814
-0-
10,800
10,800
10,800
6,000
6,000
6,000
6,200
6,200
2,000
1,000
1,000
200
35,775
35,775
7,155
107,908
43,163
43,163
4,180
4,180
4,180
83,872
38,893
12,958
$ 782,808
$ 363,005
$ 120,942
That the required financial guarantee for the above items be reduced as detailed above from $363,005 to
$120,942 to reflect the completed work. Letter of Credit No. FGAC-03062 may be reduced accordingly.
RESOLUTION NO. 2004-017
CASCADES (2002058)
Page Two
FURTHER BE IT RESOLVED that the financial guarantee requirements for the following items per Section
8.1 of the approved development contract remain as follows:
ORIGINAL CURRENT NEW
ITEM AMOUNT AMOUNT AMOUNT
Maintenance of Erosion and Sediment
Control Plan, Street Sweeping, and Storm
Sewer Cleaning (see Grading Permit for
Financial Guarantee Requirements)
Cash: $ -0- $ -0- $_0_
Financial
-0-
Financial Guarantee: $ -0- $ -0- $_0_
FURTHER
-0-
FURTHER BE IT RESOLVED THAT the sanitary sewer, watermain, and storm sewer is accepted for
continual maintenance as of January 13, 2004 subject to the two-year guarantee by the Developer per
Maintenance Bond No. 54134423 issued by United Fire and Casualty Company.
Adopted by the City Council on January 13, 2004.