HomeMy WebLinkAboutCity Council Resolution 2006-344CITY OF PLYMOUTH
RESOLUTION NO. 2006-344
REQUEST FOR PAYMENT NO. 2 AND FINAL
TIMBER CREEK EROSION CONTROL PROJECT
CITY PROJECT NO. 4137
WHEREAS, the City of Plymouth as owner and Minger Constriction, Inc., as contractor,
have entered into an agreement for the Boulder Ridge Pond Outlet Stricture Project, City
Project No. 4137, said agreement being dated January 24, 2006; and
WHEREAS, the Engineering Division has certified acceptance of the work and approval
of the final request for payment.
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF
THE CITY OF PLYMOUTH, MINNESOTA:
1. That the original contract amount was $161,987.95. The work to date is
$165,052.40 and is herewith approved. This project exceeds the original
contract amount by $3,064.45 or 1.8%, due to the need for more materials.
2. That the work performed by the contractor for the Timber Creek Erosion
Control Project (4137) and certified to the Council by the Engineering
Division as acceptable, being the same, is hereby released from the
Engineering Division as acceptable from the contract except as to the
conditions of the performance bond, any and all legal rights of the owner,
required guarantees and correction of faulty work after final payment.
3. Request for Payment No. 2 and Final in the amount of $15,565.72 to
Minger Constriction, Inc. for the Timber Creek Erosion Control Project is
hereby approved and the City Finance Director is hereby authorized and
directed to pay the same forthwith.
Adopted by the City Council on September 12, 2006.