HomeMy WebLinkAboutCity Council Resolution 2006-330CITY OF PLYMOUTH
RESOLUTION NO. 2006-330
REQUEST FOR PAYMENT NO. 2 AND FINAL
2006 TEMPORARY OVERLAY PROJECT
CITY PROJECT NO. 6109
WHEREAS, the City of Plymouth as owner and FPI Paving Contractors, Inc. as contractor,
have entered into an agreement for the 2006 Temporary Overlay Project, City Project No.
6109, said agreement was approved by the City Council on June 13, 2006; and
WHEREAS, the Engineer has certified his acceptance of the work and his approval of the final
request for payment.
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PLYMOUTH, MINNESOTA:
1. That the original contract amount was $244,637.09 and the value of the work to
date is $237,265.11 and is herewith approved. This project is below the original
contract amount by 3%.
2. That the work performed by the contractor for the 2006 Temporary Overlay
Project and certified to the Council by the engineer as acceptable, being the
same, is hereby released from the contract except as to the conditions of the
performance bond, any and all legal rights of the owner, required guarantees and
correction of faulty work after final payment.
3. Request for Payment No. 2 and Final in the amount of $11,863.26 to FPI Paving
Contractors, Inc. for the 2006 Temporary Overlay Project is hereby approved
and the City Finance Director is hereby authorized and directed to pay the same
forthwith. Funding will be from the Street Replacement Fund.
Adopted by the City Council on August 22, 2006.