HomeMy WebLinkAboutCity Council Resolution 2006-197CITY OF PLYMOUTH
RESOLUTION NO. 2006-197
APPROVING CHANGE ORDER NO. 3
PLYMOUTH METROLINK STATION 73 TRANSIT FACILITY
CITY PROJECT NO. 3125
WHEREAS, Change Order No. 3 has been prepared providing for the change in date of
substantial completion and liquidated damages:
WHEREAS, Change Order No. 3 for The Plymouth Metrolink Station 73 Transit Facility City
Project No. 3125, is recommended for approval;
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PLYMOUTH, MINNESOTA: That Change Order No. 3 for Plymouth Metrolink Station 73
Transit Facility City Project No. 3125, by changing the substantial completion date and the
liquidated damages date as follows:
1. Revise the date of Substantial Completion to be August 25, 2006 in lieu of June 16, 2006.
2. Liquidated damages are to begin everyday after September 22, 2006 in lieu of July 14,
2006.
Original Contract Stahl Constriction
$4,360,000
Change Order No. 1 January 10, 2006
64,500
Change Order No. 2 March 28, 2006
47,047
Change Order No. 3 May 23, 2006
-0-
Total Revised Stahl Construction Contract
$4,471,547
Adopted by the City Council on May 23, 2006.