HomeMy WebLinkAboutCity Council Resolution 2007-193CITY OF PLYMOUTH
RESOLUTION NO. 2007-193
APPROVING CHANGE ORDER NO. 7 AND NO. 8
PLYMOUTH METROLINK STATION 73 TRANSIT FACILITY
CITY PROJECT NO. 3125
WHEREAS, Change Order No. 7 and No. 9 for The Plymouth Metrolink Station 73 Transit
Facility City Project No. 3125, is recommended for approval;
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PLYMOUTH, MINNESOTA: That Change Order No. 7 and No. 8 for Plymouth
Metrolink Station 73 Transit Facility City Project No. 3125, by changing the Stahl
Constriction contract amount by $19,725 for a total constriction contract amount of
$4,669,539 is approved.
Original Contract Stahl Constriction
$4,360,000
Change Order No.
1 January 10, 2006
64,500
Change Order No.
2 March 28, 2006
47,047
Change Order No.
3 May 23, 2006
-0-
Change Order No.
4 August 8, 2006
54,312
Change Order No.
5 October 10, 2006
92,209
Change Order No.
6 December 12, 2006
31,746
Change Order No.
Change Order No.
7 March 15, 2007
8 April 3, 2007
16,440
3,285
Total Revised Stahl Constriction Contract
$4,669,539
Adopted by the City Council on April 24, 2007.