HomeMy WebLinkAboutCity Council Resolution 2008-196CITY OF PLYMOUTH
RESOLUTION NO. 2008-196
APPROVING CHANGE ORDER NO. 1
SUNSET TRAIL RETAINING WALL PROJECT
CITY PROJECT NO. 8103
WHEREAS, Change Order No. 1 has been prepared providing for the following:
Excavation of 1.5' of unsuitable soils under the length of the wall and
installation of Aggregate Base Class 5 recycled material.
WHEREAS, Change Order No. 1 for the Sunset Trail Retaining Wall Project, City Project No.
8103, is recommended for approval.
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PLYMOUTH, MINNESOTA: That Change Order No. 1 for Sunset Trail Retaining
Wall Project, City Project No. 8103, by adding $3,756.35 is approved:
Original Contract Amount
Previous Change Orders
$0.00
$54,740.00
THIS CHANGE ORDER NO. 1 - Add $3,756.35
REVISED CONTRACT AMOUNT $58,496.35
Adopted by the City Council on June 24, 2008.