Loading...
HomeMy WebLinkAboutCity Council Resolution 2023-135 C ITY OF P LYMOUTH R ESOLUTION N O. 2023-135 R ESOLUTION A PPROVING F INAL C LOSEOUT FOR THE Z ACHARY W ATER T REATMENT P LANT C OATINGS R EHABILITATION P ROJECT – P HASE 2 (WA229003) WHEREAS, the City of Plymouth as the owner, and Elevation Coating, LLC as the contractor, have entered into an agreement for the Zachary Water Treatment Plant Coatings Rehabilitation Project – Phase 2. Said agreement was approved by the City Council on August 30, 2022; and WHEREAS, the City Engineer has certified his acceptance of the work and his approval of the request for final payment. NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH, MINNESOTA: 1. That the original contract amount between the owner and the contractor was $798,750 and the final contract amount is $794,793.81. 2. That the work performed by the contractor for the Zachary Water Treatment Plant Coatings Rehabilitation Project – Phase 2 and certified to the council by the engineer as acceptable, being the same, is released from the contract except as to the conditions of the performance bond, any and all legal rights of the owner, required guarantees, and correction of faulty work after final payment. 3. The total project cost is $929,908.75 which included the improvements ($794,793.81) and engineering and administration ($135,114.94). BE IT FURTHER RESOLVED: 1. The original funding for this project was from the Water Fund ($955,000). 2. That funding for this project will be from the Water Fund ($929,908.75). APPROVED by the City Council on this 23rd day of May, 2023.