R ESOLUTION N O. 2022-284
R ESOLUTION A CCEPTING T ROY L ANE C ONSTRUCTION AND U TILITIES FOR C ONTINUAL M AINTENANCE
FOR C ARLSON R IDGE (2021086)
WHEREAS, in accordance with the development contract dated March 1, 2022, Bald Eagle
Builders, Inc., developer of Carlson Ridge (2021086), has agreed to install certain improvements for said
development; and
WHEREAS, the developer has completed portions of the street, utility and site grading as noted
below; and
WHEREAS, the developer has requested a reduction and release of the required financial
guarantee to reflect the completed work; and
WHEREAS, the developer has requested reimbursement for constructing a portion of public
improvements as outlined in the development contract.
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH,
MINNESOTA that the utilities are accepted for continuous maintenance as of November 15, 2022,
subject to the two-year guarantee by the developer per Letter of Credit No. 218707.
BE IT FURTHER RESOLVED that the Troy Lane construction is accepted for continuous
maintenance as of November 15, 2022, subject to the one-year guarantee by the developer per Letter of
Credit No. 218707.
BE IT FURTHER RESOLVED that funding for the $241,996.80 reimbursement for the public
portion of the Troy Lane construction shall be from the Street Reconstruction Fund.
BE IT FURTHER RESOLVED that the financial guarantee requirements are reduced and released as
follows below and that the required guarantee and Letter of Credit No. 218707 for the items be reduced
from $1,055,748 to $388,203:
% of
Original New Original
Item Amount Amount Amount
Street Construction $91,282 54,769 60%
Troy Lane Construction $158,173 39,543 25%
Sanitary Sewer System $134,945 33,736 25%
Watermain System $141,400 35,350 25%
Storm Sewer System $125,720 31,430 25%
Boulevard and Drainage Swale Sod $10,000 10,000 100%
Pond Construction $10,635 5,318 50%
Filtration Basin $10,635 5,318 50%
Street and Traffic Control Signs $1,250 0 0%
Resolution 2022-284
Page 2
Sidewalk Improvements $16,200 9,720 60%
Trail Improvements $12,200 3,050 25%
Landscaping $14,350 14,350 100%
Street Lighting $1,000 0 0%
Erosion control $37,605 28,204 75%
Site Grading & Drainage Improvements $189,150 75,660 40%
Setting Iron Monuments ($100 per iron) $3,000 3,000 100%
Tree preservation $10,000 0 0%
Wetland Mitigation $10,000 10,000 100%
Subtotal $977,544 $359,447 37%
Design, Admin, Insp, As-Builts (8%) $78,204 $28,756
Total $1,055,748 $388,203 37%
APPROVED by the City Council on this 15th day of November, 2022.