HomeMy WebLinkAboutCity Council Resolution 2021-257
C ITY OF P LYMOUTH
R ESOLUTION N O. 2021-257
R ESOLUTION A WARDING C ONTRACT FOR THE Z ACHARY W ATER T REATMENT P LANT
C OATINGS R EHABILITATION P ROJECT
WHEREAS, pursuant to an advertisement for bids for the Zachary Water Treatment Plant
Coatings Rehabilitation Project bids were received, opened and tabulated according to State law, and
the following bids were received complying with the advertisement:
Contractor Total Base Bid & Alternate 1
$935,000.00
Champion Coatings, Inc.
TMI Coatings $1,596,200.00
Swanson & Youngdale $1,714,716.82
Classic Protective Coatings, Inc. $2,167,958.00
The Osseo Construction Co. LLC $2,340,500.00
Engineers Estimate $1,212,500.00
WHEREAS, it appears that Champion Coatings, Inc., from Prior Lake, MN is the lowest
responsible bidder, complying with the minimum qualifications; and
WHEREAS, the City Engineer recommends awarding the project to Champion Coatings, Inc.
NOW, THEREFORE BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH,
MINNESOTA:
1. That the Mayor and City Manager are authorized and directed to execute contract with
Champion Coatings, Inc. for the Base Bid plus Alternate 1 for the Zachary Water Treatment
Plant Coatings Rehabilitation Project according to the plans and specifications therefore
approved by the City Council and on file in the office of the City Engineer in the amount of
$935,000.00.
2. In addition to the Coatings Rehabilitation Project in the amount of $935,000.00 the project
shall include 17% for design and administration in the amount of $158,000.00, and 5% for
contingency in the amount of $47,000.00 for a total project cost of $1,140,000.00.
BE IT FURTHER RESOLVED that the funding for this project shall be from the Water Fund in the
amount of $1,140,000.00