HomeMy WebLinkAboutCity Council Resolution 1980-011CITY OF PLYMOUTH
Pursuant to due call and notice thereof, a regular meeting of
the City Council of the City of Plymouth, Innesota was a on the
7th day of Januar , 19 80 . The following members were
present: Mayor Hunt, Counci mem ersavenpor% Hoyt, Neils and Schneider
The following members were absen—t--mane
Councilmember Neils introduced the following Resolution and
moved its adoption:
RESOLUTION NO. 80-11
RECEIVING REPORT AND ORDERING FINAL PLANS AND SPECIFICATIONS FOR
WELL NO. 6 - PROJECT NO. 012
WHEREAS, the City Council has ordered the preparation of an engineering report
to determine the feasibility of the construction of Deep Well No. 6 (Project
012); and
WHEREAS, the City's consulting engineers, Bonestroo, Rosene, Anderlik & Associates,
have prepared and submitted said report, dated December 14, 1979, to this Council,
which report indicates that such a well is feasible;
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH,
MINNESOTA that the report on Well #6 (Project 012), as prepared by Bonestroo,
Rosene, Anderlik & Associates, Inc., be and the same is hereby accepted;
AND FURTHER that the consulting engineers be authorized and directed to proceed
with the preparations of final plans and specifications for said Well #6 to be
located on property owned by the Minnesota Department of Transportation adjacent
to Fernbrook Lane and north of 23rd Avenue as recommended in the preliminary
engineering report.
BE IT FURTHER RESOLVED that the estimated cost of this project, $243,000.00, be
appropriated from the City's Utility Trunk Fund.
The motion for the adoption of the foregoing Resolution was duly seconded by'
Councilmember Ho t , and upon vote being taken thereon, the
following voted in favor thereof: Mayor Hunt, Councilmembers Davenport,
Hoyt, Neils and Schneider
The following voted against or abstained: one
Whereupon the Resolution was declared duly passed and adopted.