HomeMy WebLinkAboutCity Council Resolution 2021-038 C ITY OF P LYMOUTH R ESOLUTION N O. 2021-038 R ESOLUTION A WARDING B IDS AND Q UOTES FOR THE F IRE S TATION 2 AND 3 C ONSTRUCTION AND R ENOVATION P ROJECT (FM210014.001 AND FM210014.002) WHEREAS, the Fire Station 2 and 3 Construction and Renovation Project was initiated in 2018-2019 with a feasibility study, prepared schematic design plans in 2020 and completed final construction plans in 2021; and WHEREAS, on December 8, 2020, the City Council authorized the advertisement for bids and quotes for the Fire Station 2 and 3 Construction and Renovation Project; and WHEREAS, bids were received, opened and tabulated according to law on January 14, 2021; and WHEREAS, a total of 251 bids and quotes were received on the project. Of the 251 bids, there were zero bids withdrawn by the contractor for calculation errors; and WHEREAS, the following bids were received, and in compliance with the advertisement: Bid Category Company Amount 1A Structure Demolition Veit and Company, Inc. $70,230 1B Selective Demolition George F Cook Construction Company $149,500 2A Concrete & Masonry Systems Steenberg-Watrud Construction, LLC $2,902,126 3A Precast Molin Concrete Products $124,949 5A Structural Steel Materials Camelot Metals Combined Bid 5B Structural Steel Labor River City Erectors, Inc. Combined Bid 5C Metal Fabrications Camelot Metals $557,660 5D Metal Fabrications Labor River City Erectors, Inc. $329,500 6B Interior Arch. Woodwork & Finish Northern Woodwork, Inc. $290,275 Carp. 6C Interior Arch. Woodwork labor Kellington Construction, Inc. $111,120 7A Air & Vapor Barrier/ Insulation Greener World Solutions, LLC. $154,300 7B Metal Panels & Metal Roofing Specialty Systems, Inc. $478,700 7D Roofing Systems Lake Area Roofing and Construction, Inc. $624,783 8A Doors, Frames, Hardware Material Kendell Door and Hardware, Inc $266,313 8B Doors, Frames, Hardware Labor Kellington Construction, Inc. $91,740 8C Storefront & Glazing MT Contracting Inc. $352,444 8D Overhead Doors Yale Mechanical LLC $140,000 9A Drywall RTL Construction $624,330 9B Tile Acoustics Associates, Inc. $249,900 9C Acoustical Ceilings Kirk Acoustics, Inc. $99,200 9D Carpet Sonus Interiors, Inc. $144,900 9E Paint & Wallcovering Superior Painting and Decorating $187,400 14A Elevator Schumacher Elevator Company $208,454 21A Fire Protection Systems Lifesaver Fire Protection $148,300 22A Plumbing Systems Modern Piping, Inc. $3,310,000 23A HVAC Systems Modern Piping, Inc. Combined 25A Building Automation Egan Company $285,900 26A Electrical Systems Choice Electric, Inc. $1,815,000 31A Earthwork Park Construction Company $515,320 32A Asphalt Paving Northland Paving $231,500 32B Site Concrete Ultra Concrete $300,000 c 32C Landscape/Irrigation Precision Landscaping, Inc. $119,150 32D Retaining Walls Precision Hardscapes, Inc. $213,751 33A Utilities US Sitework, Inc. $279,790 WHEREAS, RJM Construction (RJM) have reviewed all of the bid documents and determined them to meet all responsible bidder requirements; and WHEREAS, the project also identified 17 quote categories which were received, tabulated, reviewed, and determined them to meet all responsible bidder requirements; and Quote Category Company Amount 1C Surveying Sunde Land Surveying $38,020 1D Final Cleaning A Clean Look $30,242 1F Building Envelope Consultant-Review Only Morrison Hershfield $30,750 7C Waterproofing Allowance $78,175 7E Applied Fireproofing ANI-Midwest Fireproofing & $40,000 Insulation 7F Joint Sealants Right-Way Caulking, Inc. $19,100 9F Fluid Applied Flooring Concrete Specialties Midwest, Inc $64,801 10A Specialties, Toilet Partitions, Accessories Bartley Sales Company, Inc. $48,557 10B Fire Extinguisher and Cabinets Building Material Supply, Inc. $3,882 10C Lockers Building Material Supply, Inc. $24,075 10D Flagpoles Countryside Flagpole $11,096 10E Site and Building Signage Signart $69,579 11A Food Services Equipment Custom Stainless Steel, Inc. $34,817 12A Window Treatments American Drapery Systems, Inc. $31,720 28A Fire Alarm Siemens Industry, Inc. $48,343 28B Fiber Optic Utilities Castrejon Inc. $28,935 32E Fences and Gates Peterson Companies $44,470 WHEREAS, there were two alternates for the project as determined by the project team (architect, RJM and city staff). The project team DOES NOT recommend two alternates at a cost of $203,938; and  Alternate No. 1 – Add to provide Four-Fold doors in lieu of base bid Sectional doors OH105D, OH105E, and OH105F in Fire Station #2. ($109,490 value)  Alternate No. 2 – Add to provide Calcium Silicate Masonry Units at all indicated field locations at Fire Station #2 and Fire Station #3 in lieu of base brick-02. Calcium Silicate banding is base bid for both stations, see Exterior Elevations. ($94,448 value) WHEREAS, the project is identified in the 2021 – 2030 City’s Capital Improvement Program (CIP). At the December 8, 2020 City Council meeting, the project total was estimated at $20,063,713; and WHEREAS, the project construction cost (guaranteed maximum) tabulated and recommended by the project manager RJM Construction, includes bids, quotes, contingency, and management fees is $19,218,492; and WHEREAS, the City will manage the project soft costs which are inclusive of furniture, fixtures, equipment, consultant fees, special inspections, and contingency is $2,679,406; and WHEREAS, the overall total project cost is $21,897,898 (inclusive of construction costs, soft costs, FF&E, and contingencies). NOW, THEREFORE BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH, MINNESOTA that the bids, quotes, contingency and management fees for the construction of the Fire Station 2 and 3 Construction and renovation Project of $19,218,492 (RJM guaranteed maximum price) is accepted and approved. BE IT FURTHER RESOLVED that the overall total project cost of $21,897,898 is approved and will be financed utilizing bonds, sales tax exemption reimbursement, capital improvement funds and reserves. APPROVED by the City Council on this 26th day of January, 2021.