HomeMy WebLinkAboutCity Council Resolution 2009-282CITY OF PLYMOUTH
RESOLUTION NO. 2009-282
A RESOLUTION TO
RECEIVE ENGINEERING PROPOSALS AND
DESIGNATE THE ENGINEER FOR THE
PLYMOUTH CREEK STREAM BANK RESTORATION PROJECT
CITY PROJECT NO. 8128
WHEREAS, Plymouth Creek Stream Bank Restoration Project, City Project No. 8128 is
included in the 2009-2013 Capital Improvement Program (CIP); and
WHEREAS, the goals of the Plymouth Creek Stream Bank Restoration Project are to
determine and implement the most cost effective solution(s) to reduce phosphorus loading to Medicine
Lake through repair of severe erosion, and to reduce the flooding potential along the most downstream
portion of Plymouth Creek; and
WHEREAS, the project area extends from West Medicine Lake Drive to 1000 feet north of
26th Avenue North; and
WHEREAS, a request for proposal was sent to four engineering firms that have expertise in
water resources; and
WHEREAS, the proposals were received and evaluated by City staff, and
WHEREAS, staff recommends that Wenck Associates, Inc. be designated as the engineer for
this project.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COUNCIL OF THE
CITY OF PLYMOUTH, MINNESOTA:
Wenck Associates, Inc. is designated as the City's consulting engineer for design, environmental
and geotechnical coordination, and constriction staking for the Plymouth Creek Stream Bank
Restoration Project, City Project No. 8128 in the amount of $196,428.00.
APPROVED THIS 24TH DAY OF NOVEMBER, 2009.