HomeMy WebLinkAboutCity Council Resolution 2020-270City of Plymouth
Resolution No. 2020-270
Resolution Approving Change Orders No. 1-9 for the
Vicksburg Lane and Ferndale Road Pavement
Rehabilitation Project (ST199005)
WHEREAS, the City of Plymouth as the owner, and Valley Paving Paving, Inc. as the contractor, have entered into an agreement for the Vicksburg Lane and Ferndale Road Pavement Rehabilitation
Project. Said agreement was approved by the City Council on March 10, 2020; and
WHEREAS, changes were made during construction that are not covered under the City’s contract with Valley Paving, Inc.; and
WHEREAS, Change Order No. 1 is for the installation of geotextile fabric to stabilize roadway subgrade; and
WHEREAS, Change Order No. 2 is to salvage and reinstall a rectangular rapid flashing beacon to meet ADA/PROWAG requirements; and
WHEREAS, Change Order No. 3 is to install concrete catch basin riser rings; and
WHEREAS, Change Order No. 4 is for the complete replacement of a commercial irrigation system; and
WHEREAS, Change Order No. 5 is for the repair of two water main gate valves; and
WHEREAS, Change Order No. 6 is for the repair of a catch basin in poor condition; and
WHEREAS, Change Order No. 7 is for cement stabilization of several areas of poor subgrade of Phase 1 of construction on Vicksburg Lane; and
WHEREAS, Change Order No. 8 is for milling 6” of pavement on Vicksburg Lane to resolve issues with thicker pavement than anticipated; and
WHEREAS, Change Order No. 9 is for aggregate base stabilization measures of several areas during Phase 1 of construction on Vicksburg Lane.
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH, MINNESOTA that Change Orders No. 1-9 in the total amount of $196,540.95 are approved.
APPROVED by the City Council on this 22nd day of September, 2020.