C ITY OF P LYMOUTH
R ESOLUTION N O. 2020-240
R ESOLUTION A PPROVING A SSIGNMENT OF C ONSTRUCTION C ONTRACTS TO RJM
C ONSTRUCTION FOR THE P LYMOUTH C REEK C ENTER
R ENOVATION AND E XPANSION P ROJECT
WHEREAS, City and Contractor (RJM) have entered into that certain Standard Form of
Agreement between Owner and Construction Manager dated the June 9, 2020 (“Contract”), whereby
Contractor undertakes the construction management of project known as the Plymouth Creek Center
Renovation and Expansion (“Project”); and
WHEREAS, at its June 23, 2020 meeting the City Council authorized advertisement of bids and
quotes. The project was advertised from June 24 through July 28, 2020, and bids were publicly opened
on July 28, 2020; and
WHEREAS, the Project bid documents included the proposed contract for the Work (as defined
in the Contract); and
WHEREAS, the Contract requires that the City assign to RJM all of City’s rights in and to contracts
for the construction of the Work (as defined in the Contract) which have been competitively bid and
awarded by the City.
NOW, THEREFORE, in consideration of the mutual promise and agreements made in the
Contract and other good and valuable consideration the receipt and sufficiency of which is hereby
acknowledged:
1. City hereby grants, transfers and assigns to RJM all of its right, title and interest in and to the
contracts identified below as included in the bid documents.
2. The RJM hereby consents to and accepts this Assignment and agrees to perform all of its
obligations under the Contract for the benefit of the City. RJM will enter into the contracts
in the same form included in the bid Documents with the contractors awarded the bids,
quotes and alternates by the City.
3. This Assignment shall be binding upon and inure to the benefit of the City and RJM and their
respective heirs, successors and assigns, as the case may be.
4. This Assignment may be signed in more than one counterpart, together which shall
constitute an original document.
Bid Category Company Amount
1A Building Demolition Ramsey Companies $212,150
1B Selective Demolition Mavo Systems $162,580
2A Concrete & Masonry Systems B&D Masonry 2,102,400
3A Precast Concrete (Plank & Exterior Stairs) Wells Concrete Included in 3B
3B Precast Concrete (Panels) Wells Concrete $1,796,470
5A Structural Steel (Materials) Briese Iron Works, Inc. $1,099,850
5B Structural Steel (Labor) Red Cedar Steel Erectors $755,000
5C Misc. Metals (Materials) Standard Iron $966,762
5D Misc. Metals (Labor) Red Cedar Steel Erectors $177,000
6A Rough Carpentry Kellington Construction $259,800
6B Finish Carpentry/Millwork (Material) Focal Point Fixtures $826,730
6C Finish Carpentry/Millwork (Labor) Crossroad Construction $199,971
7A Air & Vapor Barrier Henkemeyer Coatings $180,810
7B Metal Panels Division V Sheet Metal $1,495,789
7D Roofing Systems Flynn Midwest $1,254,441
7E EIFS/DEF’s Olympic Companies Included in 9A
7F Applied Fireproofing Structural Applicators $189,672
8A Translucent Wall System To Be Re-Bid $750,000
8B Doors, Frames, Hardware (Materials) Kendell Doors $378,900
8C Doors, Frames, Hardware (Labor) Ebert Construction $118,800
8D Storefront Glass & Glazing Top Lite Contract Glazing $708,000
9A MS Framing & Drywall Olympic Companies $2,155,650
9B Tile Super Set Tile and Stone $360,000
9C Acoustical Ceilings Minnesota Acoustics $465,000
9D Carpet & Resilient Flooring Sonus Interiors $460,000
9E Wood Flooring H2I Group $223,682
9F Painting & Wallcovering Berg Painting $427,900
11A Gymnasium Equip Sportscon $180,737
14A Elevator Schumacher $255,978
21A Fire Protection Systems Frontier Fire Protection $396,700
22A Plumbing Systems Muska Plumbing $1,108,962
23A HVAC Systems St. Cloud Refrigeration $2,680,000
25A Building Automation Great River Automation $171,000
26A Electrical Systems Design Electric $3,877,000
26B Photovoltaic Systems Sundial Solar $187,854
27A Audio/Visual Systems Tierney $727,781
28A CCTV Minnesota Controls $136,000
28B Access Control ECSI $193,800
31A Earthwork US Sitework $1,188,973
32A Asphalt Paving Northland Paving $630,000
32B Site Concrete Ebert Construction $514,000
32C Landscape/Irrigation Autumn Ridge Landscape $348,800
33A Utilities US Sitework $609,664
Quote Category Company Amount
1C Surveying Anderson $50,750
1D Final Cleaning No Limit $50,000
3C Stained/Sealed Concrete Donlar Construction $56,000
7C Waterproofing Spec. 7 Group $101,524
7G Joint Sealants/Expansion Joints To Be Assigned $64,250
8E Overhead Coiling Doors Skold $12,200
8F Folding Fire Doors W.L. Hall $37,998
8G Fire Curtains W.L. Hall $63,467
9G Resinous Flooring QC Companies $40,520
10A Operable Partitions Hufcor $81,710
10B Toilet Partitions and Accessories Ebert Construction $128,700
10C Fire Extinguishers and Cabinets Kellington Construction $4,800
10D Lockers The Locker Guy $11,717
10E Flagpoles Countryside Flagpole $24,269
11B Appliances & Equipment To Be Assigned $70,000
11C Stage/Dance Equipment Norcostco $46,600
12A Window Treatments CE Contract $42,538
27B Structured Cabling AB COM $107,685
27C Sound Masking ECSI $7,900
28C Fire Alarm ECSI $94,460
28D Emergency Responder Radio Syst. ECSI $43,310
32D Retaining Walls Sunram Construction $125,417
33B Fencing To Be Assigned $30,000
WHEREAS, there were 10 alternates for the project as determined by the project team (architect,
RJM and staff). The project team recommends seven alternates at a cost of $317,377:
Alt 1 – install DEFS in lieu of EIFS ($68,600 value)
Alt 2 – elevator modernization ($140,873 value)
Alt 3 – existing storefront & entrance framing ($0 value)
Alt 4 – lower level window replacement ($9,796 value)
Alt 6 – front sidewalk ($32,384 value)
Alt 7 – existing door replacement ($66,724 value)
Alt 9 – security software licensing (-$1,000 value)
NOW, THEREFORE BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH,
MINNESOTA, that the assignment of construction contracts for bids, quotes and seven alternates to RJM
Construction for the Plymouth Creek Center Renovation and Expansion Project in the amount of
$41,242,448 is approved.
APPROVED by the City Council on this 25th day of August, 2020.