HomeMy WebLinkAboutCity Council Resolution 2020-239
C ITY OF P LYMOUTH
R ESOLUTION N O. 2020-239
R ESOLUTION A WARDING B IDS AND Q UOTES FOR THE P LYMOUTH C REEK R ENOVATION
AND E XPANSION P ROJECT AND AUTHORIZING THE R EBID OF T RADE C ATEGORY #8A FOR
THE T RANSLUCENT W ALL S YSTEM
WHEREAS, the Plymouth Creek Center Renovation and Expansion Project (Project) was initiated in
2016-2017 with a feasibility study, progressed to a community engagement process in 2018, prepared
schematic design plans in 2019 and completed final construction plans in 2020; and
WHEREAS, on June 23, the City Council authorized the advertisement for bids and quotes
for the Plymouth Creek Center Renovation and Expansion Project; and
WHEREAS, bids were received, opened and tabulated according to law on July 28; and
WHEREAS, a total of 278 bids and quotes were received on the project. And of the 278 bids, there
were four bids withdrawn by the contractor for calculation errors; and
WHEREAS, the following bids were received, and in compliance with the advertisement:
Bid Category Company Amount
1A Building Demolition Ramsey Companies $212,150
1B Selective Demolition Mavo Systems $162,580
2A Concrete & Masonry Systems B&D Masonry $2,102,400
3A Precast Concrete (Plank & Exterior Stairs) Wells Concrete Included in 3B
3B Precast Concrete (Panels) Wells Concrete $1,796,470
5A Structural Steel (Materials) Briese Iron Works, Inc. $1,099,850
5B Structural Steel (Labor) Red Cedar Steel Erectors $755,000
5C Misc. Metals (Materials) Standard Iron $966,762
5D Misc. Metals (Labor) Red Cedar Steel Erectors $177,000
6A Rough Carpentry Kellington Construction $259,800
6B Finish Carpentry/Millwork (Material) Focal Point Fixtures $826,730
6C Finish Carpentry/Millwork (Labor) Crossroad Construction $199,971
7A Air & Vapor Barrier Henkemeyer Coatings $180,810
7B Metal Panels Division V Sheet Metal $1,495,789
7D Roofing Systems Flynn Midwest $1,254,441
7E EIFS/DEF’s Olympic Companies Included in 9A
7F Applied Fireproofing Structural Applicators $189,672
8A Translucent Wall System To Be Re-Bid $750,000
8B Doors, Frames, Hardware (Materials) Kendell Doors $378,900
8C Doors, Frames, Hardware (Labor) Ebert Construction $118,800
8D Storefront Glass & Glazing Top Lite Contract Glazing $708,000
9A MS Framing & Drywall Olympic Companies $2,155,650
9B Tile Super Set Tile and Stone $360,000
9C Acoustical Ceilings Minnesota Acoustics $465,000
9D Carpet & Resilient Flooring Sonus Interiors $460,000
9E Wood Flooring H2I Group $223,682
9F Painting & Wallcovering Berg Painting $427,900
11A Gymnasium Equip Sportscon $180,737
14A Elevator Schumacher $255,978
21A Fire Protection Systems Frontier Fire Protection $396,700
22A Plumbing Systems Muska Plumbing $1,108,962
23A HVAC Systems St. Cloud Refrigeration $2,680,000
25A Building Automation Great River Automation $171,000
26A Electrical Systems Design Electric $3,877,000
26B Photovoltaic Systems Sundial Solar $187,854
27A Audio/Visual Systems Tierney $727,781
28A CCTV Minnesota Controls $136,000
28B Access Control ECSI $193,800
31A Earthwork US Sitework $1,188,973
32A Asphalt Paving Northland Paving $630,000
32B Site Concrete Ebert Construction $514,000
32C Landscape/Irrigation Autumn Ridge Landscape $348,800
33A Utilities US Sitework $609,664
WHEREAS, RJM Construction (RJM) have reviewed all of the bid documents and determined them to
meet all responsible bidder requirements; and
WHEREAS, the project also identified 23 quote categories which were received, tabulated, reviewed,
and determined them to meet all responsible bidder requirements; and
Quote Category Company Amount
1C Surveying Anderson $50,750
1D Final Cleaning No Limit $50,000
3C Stained/Sealed Concrete Donlar Construction $56,000
7C Waterproofing Spec. 7 Group $101,524
7G Joint Sealants/Expansion Joints To Be Assigned $64,250
8E Overhead Coiling Doors Skold $12,200
8F Folding Fire Doors W.L. Hall $37,998
8G Fire Curtains W.L. Hall $63,467
9G Resinous Flooring QC Companies $40,520
10A Operable Partitions Hufcor $81,710
10B Toilet Partitions and Accessories Ebert Construction $128,700
10C Fire Extinguishers and Cabinets Kellington Construction $4,800
10D Lockers The Locker Guy $11,717
10E Flagpoles Countryside Flagpole $24,269
11B Appliances & Equipment To Be Assigned $70,000
11C Stage/Dance Equipment Norcostco $46,600
12A Window Treatments CE Contract $42,538
27B Structured Cabling AB COM $107,685
27C Sound Masking ECSI $7,900
28C Fire Alarm ECSI $94,460
28D Emergency Responder Radio Syst. ECSI $43,310
32D Retaining Walls Sunram Construction $125,417
33B Fencing To Be Assigned $30,000
WHEREAS, there were 10 alternates for the project as determined by the project team (architect,
RJM and staff). The project team recommends seven alternates at a cost of $317,377; and
Alt 1 – Install DEFS in lieu of EIFS ($68,600 value)
Alt 2 – Elevator modernization ($140,873 value)
Alt 3 – Existing storefront & entrance framing ($0 value)
Alt 4 – Lower level window replacement ($9,796 value)
Alt 6 – Front sidewalk ($32,384 value)
Alt 7 – Existing door replacement ($66,724 value)
Alt 9 – Security software licensing (-$1,000 value)
WHEREAS, bid category #8A (translucent wall system) did not receive a legal bid and will need to be
rebid. The project is carrying $750,000 to cover material cost and labor for the work in this category; and
WHEREAS, the project is identified in the 2020 City’s Capital Improvement Program (CIP). At the
October 8, 2019 City Council meeting, the project was authorized at $51,974,500; and
WHEREAS, the project construction cost tabulated and recommended by the project
manager RJM Construction, includes bids, quotes, recommended alternates, contingency, and
management fees is $41,242,448; and
WHEREAS, the City will manage the project soft costs which are inclusive of furniture,
fixtures, equipment, consultant fees, special inspections, playground and contingency is
$7,502,184; and
WHEREAS, the overall project cost is $48,744,632 (inclusive of construction costs and soft
costs) which is $3,226,868 under budget.
NOW, THEREFORE BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH,
MINNESOTA, that the bids, quotes and recommended alternates for the construction of the Plymouth
Creek Center Renovation and Expansion Project for $41,242,448 is approved.
BE IT FURTHER RESOLVED that the overall project cost is $48,744,632 and will be financed
utilizing General Obligation Tax Abatement Bonds, sales tax exemption reimbursement, lodging tax
revenue and potential state bonds.
BE IT FURTHER RESOLVED that staff is authorized to re-bid trade category #8A for the
translucent wall system.
APPROVED by the City Council on this 25th day of August, 2020.