WHEREAS, public improvement projects have been undertaken by the City of Plymouth; and
WHEREAS, the projects have been approved by the City Council, but total project funding has not
been designated by resolution; and
WHEREAS, it is necessary to formally designate total project funding.
NOW, THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH,
MINNESOTA, that the funding is designated as follows and the transfers be recorded in the financial records
effective December 31, 2019:
From To Amount Description
General Fund ST199004.001 - Public Works Mill & Overlay
Streets Capital Projects $104,571
$104,571
PR140003.191 - 2019 Misc. Boardwalks, Plymouth Dog Park
Park Replacement General Capital Projects $59,950
PR150002.191 - 2019 Parking Lot Repair/Replacement
Park Replacement General Capital Projects $138,016
PR170001.191 - Park Building renovation and Repair
Park Replacement General Capital Projects $12,887
PR199002.001 - 2019 Trail Repair
Park Replacement General Capital Projects $11,308
PR199004.001 - 2019 Miscellaneous Park Improvements
Park Replacement General Capital Projects $67,615
PR209004 – Misc. Park Improvements
Park Replacement General Capital Projects $8,016
Park Dedication General Capital Projects $21,846 PR140005.200 - Northwest Greenway Trail, NWG Shelter
Building
Park Dedication PR160002.181 - 2018 Park Lighting - East Medicine Lake
General Capital Projects $41,235
Park Dedication General Capital Projects $16,935 PR200001.181 - The Meadows - Community/Playfield
Park Dedication General Capital Projects $63,573 PR201801 - Camelot Nine 1st (Pulte) Trail Reimbursement
Park Dedication General Capital Projects $23,285 PR201802 - Wayzata New Elementary (CSAH 101) Trail
Reimbursement
Park Dedication General Capital Projects $4,490 PR201901 - Plymouth Reserve Development Trail
Reimbursement
IC180002.191 - 2019 LED Lighting
Ice Center General Capital Projects $172,171
FH190002 - Field House Asphalt & Concrete Repair
Field House General Capital Projects $72,232
$713,558
ST1899004.001 - Public Works Mill & Overlay
Streets Capital Projects Minnesota State Aid $2,997
ST199004.001 - Public Works Mill & Overlay
Streets Capital Projects Minnesota State Aid $309
$3,306
NCIP1903 - PWYBA - Baseball Donations
General Capital Projects Park Replacement $3,302
NCIP1904 - PWYSA - Softball Donations
General Capital Projects Park Replacement $1,067
NCIP1905 - Fusion Soccer - Soccer Donations
General Capital Projects Park Replacement $63
$4,432
Streets Capital Projects Street Reconstruction STR05122 - CR 24 - Olive Ln to Jewel Ln
$59,184
$59,184
General Capital Projects Park Dedication $104 PR189001.001 - New Trails, Medina Rd Trail - Greenwood Elem
to Brockton Ln
General Capital Projects Park Dedication $96 PR189001.002 - New Trails, Revere Ln from Hwy 55 to 6th Ave
Trail
$200
Minnesota State Aid Streets Capital Projects $50,985 NCIP1901 - County Road 47 Corridor Study, City Project
ST190013
Minnesota State Aid Streets Capital Projects $207,458 ST170003 - 54th Ave from Peony Ln to Yellowstone Ln
Minnesota State Aid Streets Capital Projects $309 ST199005 - Vicksburg Lane Full Depth Reclamation
Street Reconstruction Streets Capital Projects $219,507 ST080006 - Rail X-ing Safety Improvements
ST110010.181 - 2018 Concrete Sidewalk Replacement
Street Reconstruction Streets Capital Projects $370
Street Reconstruction Streets Capital Projects $46,784 ST110010.191 - 2019 Concrete Sidewalk Replacement
ST180002 - Troy Lane from 54th Avenue to CR 47
Street Reconstruction Streets Capital Projects $16,348
ST189001.001 - Kilmer Park Street Reconstruction
Street Reconstruction Streets Capital Projects $271,028
ST199001.001 - Candlelight Terrace Street Reconstruction
Street Reconstruction Streets Capital Projects $38,979
ST199003 - Replace Retaining Wall - Rockford Road
Street Reconstruction Streets Capital Projects $100,166
ST199005 - Vicksburg Lane Full Depth Reclamation
Street Reconstruction Streets Capital Projects $183,634
Street Reconstruction Streets Capital Projects $38,246 ST200004 - Peony Ln & Schmidt Lake Rd Intersection
Improvements
Street Reconstruction Streets Capital Projects $15,547 ST209005 - Schmidt Lake Rd & Zachary Ln Pavement
Rehabilitation
STR10015 - Peony Lane Corridor Study
Street Reconstruction Streets Capital Projects $15,643
Street Reconstruction Streets Capital Projects $115 STR16001 - Vicksburg Lane Reconstruction - Schmidt Lake Rd
to Maple Grove
Street Reconstruction Streets Capital Projects $6,714 ST189003.001 - 11th Ave and CR 101 Retaining Wall
Replacement
Street Reconstruction Streets Capital Projects $1,102,994 ST190003 - Rockford Road at I-494 Bridge Replacement
$2,314,827
Water Sewer Construction Utility Trunk Expansion $58,375 WTR15022 - Water Meter Conversion
$58,375
Water Water Sewer Construction $144,093 WA189001.001 - Well #4 Rehabilitation
Water Water Sewer Construction $146,183 WA189001.002 - Well #2 Rehabilitation
Water Water Sewer Construction $1,296,989 WA190001 - Refurbish Central Water Tower
WA199001.001 - Well #6 Rehabilitation
Water Water Sewer Construction $109,920
Water Water Sewer Construction $71,739 WA199001.002 - Well #17 Rehabilitation
WA199003 - Treatment Plant(s) Refurbishing
Water Water Sewer Construction $124,057
WA209003 - Treatment Plant Refurbishing - Zachary HSPs
Water Water Sewer Construction $3,309
SS190001 - Ferndale North Lift Station Generator
Sewer Water Sewer Construction $18,600
SS190002 - Kingswood Farms Lift Station Generator
Sewer Water Sewer Construction $18,860
SS190003 - Mission Farm Lift Station Replacement Pump
Sewer Water Sewer Construction $73,115
$2,006,864
NCIP1902 - Bass & Pomerleau Lake Alum Treatment
Water Resources Water Resources Construction $581
WRS12036 - Plymouth Meadows Pond Maintenance
Water Resources Water Resources Construction $37,148
Water Resources Water Resources Construction $68,108 WR170004 - French Ridge Park Drainage Improvement
WR180001 - St. Mary's Addition Drainage Improvement
Water Resources Water Resources Construction $108,868
Water Resources Water Resources Construction $35,782 WR180007 - Ivanhoe/Pleasant Hills Drainage Improvement
WR180009 - Meadow Wood Drainage Improvement
Water Resources Water Resources Construction $12,236
WR190001 - 19th Avenue/Dunkirk Lane Pond Improvement
Water Resources Water Resources Construction $14,823
WR200001 - Maple Creek Stream Restoration
Water Resources Water Resources Construction $17,582
WR200002 - Plymouth Marketplace Drainage Improvement
Water Resources Water Resources Construction $6,034
Sewer Water Resources Construction $111,938 WR160003 - 15th Ave/Pineview Lane Storm Sewer
Replacement
$413,099
Water STR05122 - CR24 - Olive Ln to Jewel Ln
Streets Capital Projects $14,501
Water STR13002 - TH 55 Frontage Road Reconstruction
Streets Capital Projects $12,710
Water Sewer Construction Water $144,093 Construction In Progress Transferred - Well #4 Rehabilitation
Water Sewer Construction Water $146,183 Construction In Progress Transferred - Well #2 Rehabilitation
Water Sewer Construction Water $1,313,719 Construction In Progress Transferred - Central Water Tower
Rehabilitation
Water Sewer Construction Water $109,920 Construction In Progress Transferred - Well #6 Rehabilitation
Water Sewer Construction Water $71,739 Construction In Progress Transferred - Well #17 Rehabilitation
Water Sewer Construction Water $124,057 Construction In Progress Transferred - Treatment Plants
Rehabilitation
Water Sewer Construction Water $3,309 Construction In Progress Transferred - Treatment Plants
Rehabilitation
$1,940,231
Water Resources Construction Water Resources $80,099 Construction In Progress Transferred - Plymouth Creek Stream
Restoration
Water Resources Construction Water Resources $111,974 Construction In Progress Transferred - Pass & Pomerleau Lk
Alum Treatment
Water Resources Construction Water Resources $822,324 Construction In Progress Transferred - 15th Ave/Pineview Ln SS
Replacement
Water Resources Construction Water Resources $68,108 Construction In Progress Transferred - Ridge Park Drainange
Improvement
Water Resources Construction Water Resources $108,868 Construction In Progress Transferred - St Mary Addition
Drainage Improvement
Water Resources Construction Water Resources $541,579 Construction In Progress Transferred - Elm Creek Stream
Restoration
Water Resources Construction Water Resources $35,782 Construction In Progress Transferred - Ivanhoe/Pleasant Hills
Drainage Improvement
Water Resources Construction Water Resources $12,236 Construction In Progress Transferred - Meadow Wood
Drainage Improvement
Water Resources Construction Water Resources $14,823 Construction In Progress Transferred - 19th Ave/Dunkirk Ln
Pond Improvement
Water Resources Construction Water Resources $17,582 Construction In Progress Transferred - Maple Creek Stream
Restoration
Water Resources Construction Water Resources $6,034 Construction In Progress Transferred - Plymouth Marketplace
Drainage Improvement
Water Resources Construction Water Resources $37,148 Construction In Progress Transferred - Plymouth Meadows
Pond Maintenance
Water Resources Construction Water Resources $23,094 Construction In Progress Transferred - Plymouth Creek Stream
Restoration
$1,879,651
Water Sewer Construction Sewer $47,431 Construction In Progress Transferred - Refurbish Bass Lk Plaza
LS
Water Sewer Construction Sewer $58,359 Construction In Progress Transferred - 2018 Sanitary Sewer
Lining
Water Sewer Construction Sewer $18,600 Construction In Progress Transferred - Ferndale N LS Generator
Water Sewer Construction Sewer $18,860 Construction In Progress Transferred - Kingswood Farm LS
Generator
Water Sewer Construction Sewer $73,115 Construction In Progress Transferred - Mission Farm LS
Replacement Pump
Water Sewer Construction Sewer $1,098,035 Construction In Progress Transferred - 2019 Sanitary Sewer
Lining
Water Sewer Construction Sewer $373,906 Construction In Progress Transferred -Refurbish Green Tree LS
$1,688,306
Central Equipment ST199004.001 - Public Works Mill & Overlay
Streets Capital Projects $40,421
$40,421
Information Technology IT170003 - Public Safety Body Cameras
General $33,373
Information Technology IT170003 - Public Safety Body Cameras
General Capital Projects $117,835
Information Technology IT170003 - Public Safety Body Cameras
Resource Planning $106,831
$258,039
TOTAL
$11,485,064
APPROVED by the City Council on this 28th day of July, 2020.