HomeMy WebLinkAboutCity Council Resolution 2009-033CITY OF PLYMOUTH
RESOLUTION No. 2009-033
A RESOLUTION TO APPROVE CHANGE ORDER NOS. 8-10 AND
WORK ORDER NOS. 4 AND 5
FERNBROOK LANE STREET AND SIGNAL IMPROVEMENTS
S.P. 155-164-011 AND S.P. 155-164-014
CITY PROJECT NO. 1013
WHEREAS, Change Order No. 8 has been prepared providing for the following:
Compensation to the contractor to furnish additional detour signing and winter traffic control; and
WHEREAS, Change Order No. 9 has been prepared providing for the following:
Compensation to the contractor for a fuel escalation cost in April and May 2008, Misc. grading
operations, remove and replace damaged curb and gutter, bituminous curb ramping, loss of production,
modifications to a catch basin and repair of a roof drain connection; and
WHEREAS, Change Order No. 10 has been prepared providing for the following:
Compensation to the contractor for a fuel escalation cost in June 2008 and additional common
excavation during watermain work; and
WHEREAS, Work Order No. 4 has been prepared providing the following:
Compensation to the contractor for extra items required to alter catch basins to properly drain the
parking lot at 3 13 1 Fernbrook Lane; and
WHEREAS, Work Order No. 5 has been prepared providing for the following:
Compensation to the contractor for providing a luminaire arm appropriate to not conflict with the
overhead power lines at Harbor Lane; and
WHEREAS, Change Order Nos. 8-10 and Work Order Nos. 4 & 5 for Fernbrook Lane, Street and Signal
Improvements, City Project No. 1013, are recommended for approval.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COUNCIL OF THE CITY OF
PLYMOUTH, MINNESOTA: That Change Order Nos. 8-10 and Work Order Nos. 4 & 5 for Eureka
Constriction, Inc., for City Project No. 1013, by increasing the contract amount by $56,585.69 is approved:
Resolution No. 2009-033
Page 2 of 2
Original Contract Amount $3,637,704.68
Previous Change Orders and Work Orders
243,571.94
This Change Order No. 8
7,262.34
This Change Order No. 9
20,300.96
This Change Order No. 10
23,429.15
This Work Order No. 4
4,907.05
This Work Order No. 5
686.19
Revised Contract Amount $3,937,862.31
APPROVED THIS I OTH DAY OF FEBRUARY.