1. CALL TO ORDER
2. TOPICS
2.1 Four Seasons Mall redevelopment project update
Four Seasons Mall Redevelopment PowerPoint
Analysis memo from Ehlers 10-25-19
2.2 Set future Study Sessions
November
December
January
3. ADJOURN
1
Special City
Council
October 30, 2019
Agenda
Number:2.1
To:Dave Callister, City Manager
Prepared by:James Barnes, Housing Program Manager
Reviewed by:Steve Juetten, Community Development Director
Item:Four Seasons Mall redevelopment project update
1. Action Requested:
Receive an update on the Four Seasons Mall redevelopment project.
2. Background:
Attached is a PowerPoint presentation which provides a high level overview of the Four Seasons
Mall Redevelopment project and action items that Council will be considering on November 12 and
future meetings.
3. Budget Impact:
N/A
4. Attachments:
Four Seasons Mall Redevelopment PowerPoint
Analysis memo from Ehlers 10-25-19
2
Four Seasons Mall
Redevelopment
Dominium Development
3
Council Action
(Nov 12)
•Consider PUD & preliminary plat
•Hold public hearing for and approve sale of housing revenue bonds
•Approve TIF redevelopment agreement term resolution
4
Council Action
(Future Council Meetings)
•Execute Bassett Creek Watershed grant documents & maintenance agreements
•Approve purchase agreement and related documents for parking ramp and site
•Execute DEED Redevelopment Fund grant documents
•TIF Redevelopment Agreement
•Approve TIF interfund loan agreement for pooled funds (if needed)
•Approval of final plat
•Public hearing on roadway vacation
5
6
7
8
Housing Overview
•1 person household = $35,000 - $49,000
•2 person household = $40,000 - $56,000
•3 person household = $45,000 - $63,000
•4 person household = $50,000 - $70,000
•1 bedroom rents = $915 - $1,315
•2 bedroom rents = $1,095 - $1,576
•3 bedroom rents = $1,261 - $1,816
Two – three story family housing buildings with 163 units
One – six story senior housing building with 255 units
Affordable to households at 50–70 % of the area median income
9
Commercial Overview
•Developed by Launch LLC
•Approximately 23,300 sq. ft. of space
•Four individual buildings
•Possible uses include
•Coffee shop
•Fast casual sit down restaurant
•Sit down restaurant
•General retail space
10
Parking Ramp
•Three Story 229 stall parking ramp
•200 stalls for park & ride customers during weekdays
•Available to the commercial visitors and general public during non park and
ride hours.
•Early cost estimates are between $7.8 - $8.2 million
11
12
Park & Ride Facility
Deal Points
•City will acquire property from Dominium
•City will enter into agreements with Architectural and Engineering firms
•Public bidding process
•City will hire a Project Manager
•City will build ramp
•Execute Operations and Maintenance Agreement
13
Housing Revenue Bonds
•Council granted preliminary approval on July 23, 2019
•Received 10% allocation for the family buildings
•Sale must occur by December 3, 2019
•Application will be submitted in January for remaining 90% and the senior
building
•Housing Revenue Bonds are pass-through and do not affect the city’s credit
rating.
14
TIF Redevelopment Agreement
Terms
•Pay-As-You-Go TIF Notes over 18 years (75% of annual increment)
•Family Note not to exceed $1,904,000 (present value)
•Senior Note not to exceed $3,127,000 (present value)
•Increment could be collected beyond 18 years if additional eligible uses were identified
•Minimum Assessment Agreement will be in place
•Affordability maintained for a minimum of 20 years
•City receives 25% of increment to assist with public improvements including ramp and roadway improvements ($1,651,000 - present value)
15
DEED Redevelopment Fund
Grant Documents
•Project awarded $637,450 in DEED Redevelopment Grant funds
•Funds may be used for
•Demolition
•Abatement
•Water infiltration pond
•Utilities (water, storm sewer, and sanitary sewer)
•Developer will execute a sub-grant agreement
16
Bassett Creek Watershed
Grant Documents & Maintenance Agreements
•$840,000 available grant funds to assist with storm water quality
improvements
•The goal is to reduce 100 pounds of phosphorus from the north arm of
Bassett Creek
•Construction of new storm water pond and enhancements to nearby
wetlands
•Watershed is expected to act on the grant November 14, 2019
17
Council Action
(Nov 12)
•Consider PUD & preliminary plat
•Hold public hearing for and approve sale of bonds
•Approve TIF redevelopment agreement term resolution
18
Council Action
(Future Council Meetings)
•Execute Bassett Creek Watershed grant documents & maintenance agreements
•Approve purchase agreement and related documents for parking ramp and site
•Execute DEED Redevelopment Fund grant documents
•TIF Redevelopment Agreement
•Approve TIF interfund loan agreement for pooled funds (if needed)
•Approval of final plat
•Public hearing on roadway vacation
19
Memo
To: Jim Barnes, HRA Manager
From: Keith Dahl and Stacie Kvilvang, Ehlers
Date: October 24, 2019
Subject: Four Seasons Mall Redevelopment Projects – Analysis of TIF Request
The City received two (2) applications for public financial assistance from Dominium (the
“Developer”) requesting approximately $8.1 million of Tax Increment Financing (TIF)
assistance in the form of two (2) pay-as-you-go (PAYGO) TIF Notes over a 26-year term. The
Developer has proposed to construct a 255-unit affordable senior apartment, along with a
163-unit, non-age restricted affordable apartment on the above referenced site (the
“Projects”). Construction would begin in the spring of 2020 with an anticipated project costs
of approximately $131 million (taxable value of $75.5 million).
We have conducted a review of the Projects, specifically the Developer’s budget and pro
forma based on industry standards for construction, land acquisition, and project costs; as
well as to ensure that all revenues, and expenditures have been appropriately accounted for
and considered.
A TIF estimate was prepared to determine the potential amount of increment that could be
generated from the Projects. Based upon only providing 75% of the TIF (City retains 25% for
other redevelopment projects and administrative costs), the Projects would generate a total
present value (principal amount) of approximately $6.775 million (this figure is based on the
developer’s anticipated financing rate of 4.312%).
Based on our review, the Developer’s requested financial assistance is more than what is
necessary for the Projects to be “financially feasible”. We’ve concluded that the Projects
require only 18 years of assistance totaling approximately $5.027 million ($3.127 million for the
sr. apartments and $1.9 million for the non-age restricted apartments).
The tables below provide a synopsis of the sources and uses associated with the Projects:
Senior
SOURCES - SR. APTS
Amount Pct. Per Unit
First Mortgage 40,935,001 55% 160,529
TIF Mortgage 3,127,000 4% 12,263
Tax Credits 20,984,532 28% 82,292
Deferred Developer Fee (100% of Total Fee) 6,398,982 9% 25,094
Deferred Contractor Fee (91% of Total Fee) 2,827,128 4% 11,087
Local Grants 400,000 1% 1,569
TOTAL SOURCES 74,672,643 100% 292,834
20
USES - SR. Apts
Amount Pct. Per Unit
Acquisition Costs 2,699,254 4% 10,585
Construction Costs 51,567,746 69% 202,226
Contractor Fee 3,123,832 4% 12,250
Environmental Abatement/Soil Correction 530,000 1% 2,078
Professional Services 2,292,445 3% 8,990
Financing Costs 6,993,238 9% 27,424
Developer Fee 6,398,982 9% 25,094
Cash Accounts/Escrows/Reserves 1,067,146 1% 4,185
TOTAL USES 74,672,643 100% 292,834
Non-Age Restricted
SOURCES - NON-AGE RESTRICTED APTS
Amount Pct. Per Unit
First Mortgage 30,176,000 54% 185,129
TIF Mortgage 1,904,000 3% 11,681
Tax Credits 15,799,202 28% 96,928
Deferred Developer Fee (100% of Total Fee) 4,927,616 9% 30,231
Deferred Contractor Fee (100% of Total Fee) 2,382,686 4% 14,618
Local Grants 1,067,450 2% 6,549
TOTAL SOURCES 56,256,954 100% 345,135
USES - NON-AGE RESTRICTED APTS
Amount Pct. Per Unit
Acquisition Costs 2,016,669 4% 12,372
Construction Costs 39,280,602 70% 240,985
Contractor Fee 2,387,850 4% 14,649
Environmental Abatement/Soil Correction 560,000 1% 3,436
Professional Services 1,668,545 3% 10,236
Financing Costs 4,725,464 8% 28,991
Developer Fee 4,927,616 9% 30,231
Cash Accounts/Escrows/Reserves 690,208 1% 4,234
TOTAL USES 56,256,954 100% 345,135
Pro Forma Analysis:
Overall, the information contained in the development pro formas generally meets the
expectations of a rental housing project utilizing 4% low-income housing tax credits (LIHTC)
and other sources of public financial assistance.
1. Acquisition Costs – The proposed land acquisition cost of the Projects is approximately
$11,000 to $12,000 per unit. This is within the market range of $10,000 to $15,000 per
unit for similar development projects of its type.
2. Total Development Costs (the “TDC”) – The TDC is approximately $131 million or
$313,000 per unit. Multi-family projects in this market generally range between $225,000
and $275,000 per unit. The Projects are higher than the expected market range, however 21
there are two main reasons influencing this higher value; (i) structural supports and
pilings due to poor soils; and (ii) higher than normal water table. These two reasons have
increased the construction costs associated with concrete work and pilings throughout
the site and ensuring structurally sound foundations.
3. Developer Fee – The proposed developer fee is approximately 9% of the TDC, which is
within the typical industry range of 8-10% for LIHTC projects. The Developer is limiting
its fee and deferring 100% of it to close the financial gap. Instead of the Developer being
compensated upfront for the time and resources spent to develop the Projects, they will
be paid out of available cash flow. Currently, it is anticipated to be repaid within 17 years.
4. Contractor Fee – The Developer acts as their own general contractor and have
subsequently proposed a contractor fee that is 4.2% of the TDC, which is within the
industry range of 3% to 5%, but low for a standard LIHTC project. They are deferring
100% of the fee in the non-age restricted project and 91% in the senior project, which
will be paid out of cash flow and is anticipated to be repaid within 17 years (the combined
contractor fee and developer fee equate to approximately 13% of the TDC, which
typically totals 12-14%).
5. Rents – All of the units will be affordable to households at or below 60% of the area
median income (AMI). The proposed gross rents range from $60 - $90 above the 2019
regulatory maximums allowed under the LIHTC program; however, the Developer is
projecting the regulatory maximum rents out to 2020 instead of using the 2019 rent limits
as found below. The rent and income limits are derived by the United States Department
of Housing and Urban Development (HUD) on an annual basis, and the 2020 rent limits
will not be released until April of next year.
Maximum Gross Monthly Rent
Bedroom Size 60% AMI
One Bedroom $ 1,125
Two Bedrooom $ 1,350
Three Bedroom $ 1,560
6. Operating Expenses – The operating expenses on a per unit basis for the Projects are
approximately $3,000, which at the low end of the typical market range of $3,000 to
$4,000 per unit per year. Please note that this per unit expense is before management
fees, property taxes, and replacement reserves.
7. Management Fee – The proposed management fee is 2.5% of the effective gross
income of the Projects. This is lower than the typical range of 3% to 5%.
8. Reserves – The annual deposit to replacement reserves is $250/unit per year, which is
typical for LIHTC projects.
9. Financing – The Developer has maximized the First Mortgages for each of the Projects.
The mortgages require debt coverage of 115% to ensure that revenues generated will
be adequate to repay them. In review of the Developer’s debt coverage, they have 22
approximately 111% with TIF assistance in year 1 and meet the required debt coverage
ratio of 115% in year 3.
10. Low-income Housing Tax Credits (LIHTC) – The Projects anticipate tax credit pricing
of $0.965 for every $1.00 of available tax credit, which generates approximately $36.7
million of proceeds for the Projects. Tax credit pricing on many current projects is
between $0.85 and $0.95. Based on current conditions, the assumed tax credit equity is
exceptional.
Recommendation:
Based on our review of the Developer’s pro forma and under current market conditions, the
proposed developments may not reasonably be expected to occur solely through private
investment within the near future. The cost associated with development of the Projects may
only be feasible through public financial assistance from the City. We conclude that TIF
assistance in the amount of $5.027 million, in two (2) separate PAYGO TIF Notes can be
supported for the Projects.
Please contact either of us at 651-697-8500 with any questions.
23
Special City
Council
October 30, 2019
Agenda
Number:2.2
To:Dave Callister, City Manager
Prepared by:Sandy Engdahl, City Clerk
Reviewed by:Laurie Hokkanen, Administrative Services Director
Item:Set future Study Sessions
1. Action Requested:
Schedule Study Sessions and/or add topics as desired. Calendars are attached to assist with
scheduling.
2. Background:
Pending Study Session Topics (at least three Council members have approved the following study
items on the list):
-IOCP Affordable Workforce Housing Tour
Other Council requests for Study Session Topics:
None at this time.
Staff requests for Study Session Topics:
None at this time.
3. Budget Impact:
N/A
4. Attachments:
November
December
January
24
SUN MON TUE WED THU FRI SAT
1
2
3 4 5
6 7 8 9
10 11 12
13 14
15 16
17 18 19 20
21
22 23
24 25 26 27 28 29 30
November 2019
3400 Plymouth Boulevard Plymouth, MN 55447 OFFICIAL CITY CALENDAR Phone: 763-509-5080 plymouthmn.gov
5:30 PM SPECIAL COUNCIL MEETING
Budget, CIP, Utility Rate Study Medicine Lake Room
7:00 PM REGULAR COUNCIL MEETING Council Chambers
7:00 PM PLANNING COMMISSION MEETING Council Chambers
THANKSGIVING HOLIDAY
7:00 PM ENVIRONMENTAL QUALITY COMMITTEE MEETING
Medicine Lake Room
5:30 PM SPECIAL COUNCIL MEETING Review Board and Commission Applications Medicine Lake Room 7:00 PM REGULAR COUNCIL MEETING Council Chambers
SUN TUES MON THUR FRI SAT
THANKSGIVING HOLIDAY
CITY OFFICES CLOSED
CITY OFFICES CLOSED
VETERANS DAY CITY OFFICES CLOSED
7:00 PM PARK & REC ADVISORY COMMISSION MEETING Plymouth Ice Center
7:00 PM HOUSING AND RE-
DEVELOPMENT
AUTHORITY
MEETING
Parkers Lake Room
7:00 PM PLANNING COMMISSION MEETING
Council Chambers
Plymouth Arts Fair Plymouth Creek Center
Plymouth Arts Fair
Plymouth Creek Center
25
SUN MON TUE WED THU FRI SAT
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31
December 2019
3400 Plymouth Boulevard Plymouth, MN 55447 OFFICIAL CITY CALENDAR Phone: 763-509-5080 plymouthmn.gov
7:00 PM PLANNING COMMISSION MEETING Council Chambers
5:30 PM SPECIAL COUNCIL MEETING Dundee Nursery Redevelopment Concept Plan Medicine Lake Room 7:00 PM REGULAR COUNCIL MEETING Council Chambers
7:00 PM HOUSING AND REDEVELOPMENT AUTHORITY MEETING
Parkers Lake Room
SUN TUES MON WED THUR FRI SAT
7:00 PM ENVIRONMENTAL QUALITY COMMITTEE MEETING Council Chambers 7:00 PM CHARTER COMMISSION MEETING Medicine Lake Room
7:00 PM PLANNING COMMISSION MEETING
Council Chambers
CHRISTMAS DAY CITY OFFICES CLOSED
CHRISTMAS EVE CITY OFFICES CLOSED AT NOON
2:00 PM - 5:00 PM Old Fashioned Christmas Plymouth Creek Park
5:30 PM SPECIAL COUNCIL MEETING Board and Commission Interviews Medicine Lake Room
26
SUN MON TUE WED THU FRI SAT
1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17
18
19 20
MARTIN LUTHER KING JR. BIRTHDAY CITY OFFICES CLOSED
21 22 23 24
25
26 27 28 29 30 31
January 2020
3400 Plymouth Boulevard Plymouth, MN 55447 OFFICIAL CITY CALENDAR 763-509-5080 plymouthmn.gov
7:00 PM PARK & REC ADVISORY COMMISSION MEETING Council Chambers
SUN TUES MON WED THUR FRI SAT
CHANGES ARE NOTED IN RED
7:00 PM REGULAR COUNCIL MEETING
Council Chambers
7:00 PM PLANNING COMMISSION MEETING
Council Chambers
7:00 PM ENVIRONMENTAL QUALITY COMMITTEE MEETING Medicine Lake Room
7:00 PM HOUSING AND
REDEVELOPMENT
AUTHORITY
MEETING
Parkers Lake Room
NEW YEAR’S DAY CITY OFFICES CLOSED
7:00 PM REGULAR COUNCIL MEETING Council Chambers
Absentee Voting begins for Presidential Nomination Primary Election
6:00 PM-8:00 PM Skate the Garden Millennium Gardens Pond
6:30 PM-10:00 PM After Hours at the Creek Plymouth Creek Center
27