HomeMy WebLinkAboutCity Council Resolution 2019-036 C ITY OF P LYMOUTH R ESOLUTION N O. 2019-036 R ESOLUTION A PPROVING C HANGE O RDER N O. 1 FOR THE 15 TH A VENUE AND H WY 55 U TILITY I MPROVEMENT (WR160003) WHEREAS, a contract was awarded to Geislinger and Sons, Inc. on August 28, 2018 for the construction of the 15th Avenue and Hwy 55 Utility Improvement; and WHEREAS, changes were made during construction to the contract in the amount of $118,840.60 as a part of Change Order No. 1 that includes:  Abandoning the pipe crossing underneath Hwy 55 by using grout instead of sand.  Open cut installation of 48” HOBAS pipe in place of slip lining the existing 54” corrugated metal pipe.  Installing a new sanitary sewer manhole inside the existing sanitary sewer manhole instead of removing and replacing the existing manhole.  Lining the existing sanitary sewer pipe crossing under Hwy 55 with a cured in place pipe (CIPP) instead of pipe bursting a new pipe.  Removal of obstacles that required extra effort during pipe jacking a new storm sewer crossing under Hwy 55. WHEREAS, the City’s engineer for the project, WSB & Associates, performed additional work outside the scope of their proposal in the amount of $37,900.00 as a result of Change Order No. 1 that includes:  Additional three weeks of inspection services and administration as a result of the lengthened project schedule.  Additional design of alternatives detailed in Change Order No. 1 and review of submittals.  Additional coordination with UP Railroad. NOW, THEREFORE BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF THE CITY OF PLYMOUTH, MINNESOTA, that Change Order No. 1 in the total amount of $156,740.60 is approved. APPROVED by the City Council on this 12th day of February, 2019.